DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 1388Completed

Damac Hills - The Flora دماك هيلز - ذا فلورا Al Hebiah Third · Damac Hills by Damac Crescent PropertiesAll phases of Damac Hills Completed 25 March 2019 (DLD) DLD end date Mar 2019 DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.

Completed projects cannot be added to My units.

Completed
Mar 2019
DLD end date Mar 2019
Build time
64 months
Dec 2013 → Mar 2019
Latest sales
—
Fewer than 5 recent sales
3 BR rent
220,000 AED/yr
5 leases, 12 months
Developer
52 projects
43 completed · 6,466 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built

28 October 2026
Built
100%
Latest DLD register reading: 100% built on 28 October 2026 (register readings: 3). Latest DLD inspection: 100% built on 25 March 2019 (inspections: 12).
Every DLD inspection and every change in the register %, newest first
Date % built Source
25 March 2019 100% DLD inspection
4 October 2018 86.4% DLD inspection
6 June 2018 84.3% DLD inspection
17 January 2018 81.2% DLD inspection
6 September 2017 80.7% DLD inspection
23 May 2017 77.6% DLD inspection
20 December 2016 71.5% DLD inspection
1 August 2016 66.8% DLD inspection
17 March 2016 56.3% DLD inspection
5 October 2015 51.1% DLD inspection
13 May 2015 43% DLD inspection
23 December 2014 26.3% DLD inspection

Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 5 August 2022, 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗

Site timeline

± 6 months

Our imagery reading holds no milestone for this project yet.

Our reading of historical satellite imagery

Registered period and actual build

Registered period
64 monthsActual build
64 months
Start date
1 December 2013
DLD end date
25 March 2019
Completion date
25 March 2019
Completion vs DLD end date
On the date

Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.

Changes in the DLD register

No change to the end date, status or % built across the register exports we hold.

Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.

Building permits

50 of 67 buildings

Buildings on the project’s plots: 67, on construction permits: 67, as Dubai Municipality lists them.

Furthest stage reached: Final works.

Work not started
Site works
Foundations
Structure
Masonry
Finishes
Final works
Completed
Buildings
67
67 on construction permits
Permit status
Closed
293229
Issued
4 December 2016
Work start
20 November 2016
Completion
5 June 2018
Consultant · contractor
ENGINEERING CONSORTIUM - CONSULTING ENGINEERS · GHANTOOT GULF CONTRACTING L.L.C
Buildings by the furthest work stage Dubai Municipality lists
Work stage Buildings
Structure2
Finishes15
Final works50

Source: Dubai Municipality building permits, export of 26 October 2026. These dates and stages are Dubai Municipality’s records, not DLD’s register.

DLD registration

DLD services ↗
DLD project number
1388
Escrow agent
Abu Dhabi Commercial Bank
Zoning authority
Dubai Development Authority (DDA)
Master project
Damac Hills
DLD area
Al Hebiah Third
Units · villas
0 · 0
Start → DLD end
Dec 2013 → Mar 2019
Registered units3 bed 24 · 4 bed 10 · 5+ bed 33; sizes 2,801–5,499 sqft

Homes: villas 67.

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: Project consists of 67 freehold G+1 villas located in Dubailand. The villas are designed to have a concrete structure and block with internal and external finishes.

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft

No off-plan sales are registered for this project since 2020, so there is no launch price.

Prices are over villas and townhouses, the type most sales in this project are.

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Median AED/sqft by quarter

2020-Q1 → 2026-Q2

Median AED/sqft of registered sales per quarter (villas and townhouses). Source: DLD. Grey dashed line: DLD area Al Hebiah Third, median AED/sqft of ready sales of villas and townhouses by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

Rents and gross yield

New Ejari rent contracts for villas and townhouses in this project, 12 months to 5 November 2026, against the 12 months before. Fewer than 10 ready sales per bedroom count in those 12 months, so no yield is shown.

Bedrooms Median annual rent New contracts Change on a year earlier
3 BR AED 220,000 5 -8.3%

New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.

Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.

Mortgage registrations

Home mortgages DLD has registered on units in this project, per quarter, in the 12 quarters to 5 November 2026.

Mortgage registrations on homes per quarter. Source: DLD.

Mortgage registrations in the last 4 quarters (2026-Q1 to 2026-Q4): 4; the amount shows from 5 registrations.

Since the first registration in 2016-Q4: 48 in all.

Counts DLD's mortgage registrations on homes in this project, including pre-registrations on off-plan units and lease-to-own registrations; portfolio and developer mortgages are left out. Amounts are the values DLD registers, shown for 5 registrations or more. A registration says nothing about the lender or the terms.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

Service charges

What owners pay a year in completed buildings of the project’s master community, from their owners’ association budgets. A building’s own charge is set by its own budget.

Villa and townhouse budgets; apartment buildings’ budgets are left out.
3.96 AED/sqft a year
Damac Hills: median of 21 developments’ owners’ association budgets, 2026

Median AED per sq ft a year of residential owners’ association budgets, each development counted once, in the newest budget year with at least 10 developments. Plots, shared areas and hotel rooms are left out. A budget is not any one owner’s bill.

Source: Dubai Land Department, owners’ association budgets (service charges).

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

The newest 10 of 3 registered sales in the 12 months to 5 November 2026
DateMarketType Size (sqft) Price (AED) AED/sqft
7 May 2026readyVilla 7,634 11,500,000 1,506
11 February 2026readyVilla 7,304 12,198,780 1,670
25 November 2025readyVilla 4,324 5,950,000 1,376
31 October 2025readyVilla 4,236 5,700,000 1,346
17 October 2025readyVilla 4,236 5,500,000 1,298
5 August 2025readyVilla 6,318 11,100,000 1,757
11 March 2025readyVilla 6,888 10,777,000 1,565
26 February 2025readyVilla 7,826 14,980,000 1,914
13 January 2025readyVilla 3,519 4,655,000 1,323
23 December 2024readyVilla 7,085 11,000,000 1,553

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

LocationAl Hebiah Third · Dubai Municipality community

Park · 270 mPark · 450 mDamac Hills Park · 450 mSpinneys · 830 mDamac Hills Skate Park · 1 kmGeant Supermarket · 1.1 kmMall · 1.2 kmJebel Ali School · 1.5 kmApproximate project location© OpenStreetMap contributors · Dubai Municipality · RTA · Makani
Approximate project location Malls and supermarkets Schools and hospitals Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

Metro stationJumeirah Golf Estates Metro Station · Red Metro line · 9.5 km
MallMall · 1.2 km
SupermarketSpinneys · 830 m
HospitalMediclinic Springs · 9.5 km
SchoolJebel Ali School · 1.5 km
ParkPark · 270 m

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors · RTA

New homes within 1.5 km

Open projects within 1.5 km of the pin: 9, with 2,976 units and villas.

2024: 02026: 02027: 4792028: 02029: 1,1392030: 288No end date: 1,070

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Al Hebiah Third: 9

Open projects in the same DLD area, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Damac District 4.1% Mar 2029 1,810 737
Damac Hills - Golf Greens 2 45.2% — 1,666 348
Damac Hills - Golf Greens 1 40.5% Mar 2027 1,713 117
Damac Hills - Ivory 0.6% Jun 2028 — 98
Damac Hills - Golf Gate 2 80.4% — 1,472 84
Damac Hills - Autograph Collection 9.4% May 2027 — 32
Damac Hills - Gems Estates 1 48.8% Nov 2026 — 14
Damac Hills - Gems Estates 2 62.6% Sep 2024 — 8
DAMAC Hills - Lilac 0% Jan 2030 — 0

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Al Hebiah Third

Developer in DLD data Damac Crescent Properties · DLD developer no. 954

Projects registered
52
43 completed · 8 under construction · 1 not started
Units delivered
6,466
2,976 in the pipeline
Median build time
48 months
completed projects measured: 43
Past the DLD end date
1
of 6 under construction with a DLD end date

Completed a month or more after their DLD end date: 2 of 43 completed projects with both dates. In 31 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Damac Crescent Properties is one of 21 DLD-registered developers we list together as Damac. See the group

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Other projects in Damac Hills

DLD lists 51 projects in the master project Damac Hills.

Damac Hills - Gems Estates 2Under construction · 62.6% · Sep 2024
Damac Hills - Gems Estates 1Under construction · 48.8% · Nov 2026
Damac Hills - Golf Greens 1Under construction · 40.5% · Mar 2027
Damac Hills - Autograph CollectionUnder construction · 9.4% · May 2027
Damac Hills - IvoryUnder construction · 0.6% · Jun 2028
Damac DistrictUnder construction · 4.1% · Mar 2029
Damac Hills - Golf Gate 2Under construction · 80.4% · —
Damac Hills - Golf Greens 2Under construction · 45.2% · —
DAMAC Hills - LilacNot started · 0% · Jan 2030
Damac Hills - Queens MeadowCompleted · 100% · Dec 2014
Damac Hills - Golf VedutaCompleted · 100% · Apr 2016
Damac Hills - WhitefieldCompleted · 100% · May 2016

Questions about Damac Hills - The Flora

When was Damac Hills - The Flora completed?

Damac Hills - The Flora is recorded as completed on 25 March 2019 (DLD register of 1 November 2026).

Who is the developer of Damac Hills - The Flora?

Damac Crescent Properties, as registered with DLD.

What is the DLD project number of Damac Hills - The Flora?

1388.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error