DLD project no. 1398Completed
Dubai Hills - Hills View Community دبي هيلز-هيلز فيو كومينتى Completed 31 August 2019 (DLD) · DLD end date Aug 2019 · DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.
Completed projects cannot be added to My units.
CompletionDLD readings of % built, beside the share of the planned period gone
% built
28 October 2026| Date | % built | Source |
|---|---|---|
| 28 September 2020 | 100% | DLD inspection |
| 13 May 2019 | 97.2% | DLD inspection |
| 12 March 2018 | 92.1% | DLD inspection |
| 19 November 2017 | 91.7% | DLD inspection |
| 14 February 2017 | 48.7% | DLD inspection |
| 13 October 2016 | 29.2% | DLD inspection |
| 24 April 2016 | 23.1% | DLD inspection |
| 23 July 2015 | 15.7% | DLD inspection |
| 4 March 2015 | 14.7% | DLD inspection |
Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 5 August 2022, 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗
Site timeline
± 6 monthsOur imagery reading holds no milestone for this project yet.
Our reading of historical satellite imagery
Registered period and actual build
Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.
Changes in the DLD register
No change to the end date, status or % built across the register exports we hold.
Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.
Building permits
1 of 16 buildingsBuildings on the project’s plots: 16, on construction permits: 16, as Dubai Municipality lists them.
Furthest stage reached: Final works.
| Work stage | Buildings |
|---|---|
| Site works | 4 |
| Masonry | 1 |
| Finishes | 6 |
| Final works | 1 |
| No stage listed | 4 |
Source: Dubai Municipality building permits, export of 26 October 2026. These dates and stages are Dubai Municipality’s records, not DLD’s register.
DLD registration
DLD services ↗Homes: villas 4.
Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.
Description in the DLD register: Construction of 33 villas (Shell & Core), Dubai, UAE
DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae
Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.
AED · sqft
No off-plan sales are registered for this project since 2020, so there is no launch price.
Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.
Mortgage registrations
Home mortgages DLD has registered on units in this project, per quarter, in the 12 quarters to 5 November 2026.
| Quarter | Mortgage registrations |
|---|---|
| 2024-Q1 | 0 |
| 2024-Q2 | 2 |
| 2024-Q3 | 1 |
| 2024-Q4 | 1 |
| 2025-Q1 | 1 |
| 2025-Q2 | 1 |
| 2025-Q3 | 1 |
| 2025-Q4 | 0 |
| 2026-Q1 | 0 |
| 2026-Q2 | 1 |
| 2026-Q3 | 2 |
| 2026-Q4 | 0 |
Mortgage registrations on homes per quarter. Source: DLD.
Mortgage registrations in the last 4 quarters (2026-Q1 to 2026-Q4): 3; the amount shows from 5 registrations.
Since the first registration in 2015-Q2: 32 in all.
Counts DLD's mortgage registrations on homes in this project, including pre-registrations on off-plan units and lease-to-own registrations; portfolio and developer mortgages are left out. Amounts are the values DLD registers, shown for 5 registrations or more. A registration says nothing about the lender or the terms.
Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence
LocationHadaeq Sheikh Mohammed Bin Rashid · Dubai Municipality community
Places near the project
Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.
School ratings: KHDA’s school directory ↗ · Report a wrong location
Dubai Municipality · Makani · © OpenStreetMap contributors · RTA
New homes within 1.5 km
Open projects within 1.5 km of the pin: 7, with 1,878 units and villas.
| DLD end year | Projects | Units and villas |
|---|---|---|
| 2026 | 1 | 0 |
| 2028 | 2 | 658 |
| 2029 | 1 | 406 |
| No end date | 3 | 814 |
Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.
Open projects in Hadaeq Sheikh Mohammed Bin Rashid: 26
Open projects in the same DLD area, by registered sales in 24 months.
| Project | Built | DLD end date | AED/sqft, 12 mo | Sales, 24 mo |
|---|---|---|---|---|
| Rosehill | 7.8% | Jun 2029 | 2,245 | 531 |
| Vida Residences Club Point | 43.5% | Feb 2029 | 2,306 | 484 |
| Vida Residences Hillside | 10% | May 2029 | 2,492 | 451 |
| Parkwood | 15% | Jan 2029 | 2,416 | 403 |
| Palace Residences Hillside A | 7.9% | Jun 2029 | 2,571 | 349 |
| Hillsedge | 25.6% | Jan 2029 | 2,489 | 331 |
| Keturah Reserve | 10% | Jun 2027 | 3,682 | 318 |
| City View Dubai Hills Residences | 38.8% | Mar 2027 | 2,800 | 230 |
| Eden Hills | 3.5% | Dec 2026 | — | 153 |
| Greencrest | 1.2% | Jun 2029 | 2,225 | 145 |
| Club Place | 68.8% | Dec 2028 | 2,306 | 141 |
| Golf Hillside | 65.8% | Dec 2028 | 2,485 | 92 |
AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.
Developer in DLD data Dubai Hills Estate L.L.C · DLD developer no. 984
Completed a month or more after their DLD end date: 2 of 35 completed projects with both dates. In 23 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.
Other projects in Dubai Hills Estate
DLD lists 51 projects in the master project Dubai Hills Estate.
Questions about Dubai Hills - Hills View Community
When was Dubai Hills - Hills View Community completed?
Dubai Hills - Hills View Community is recorded as completed on 31 August 2019 (DLD register of 1 November 2026).
Who is the developer of Dubai Hills - Hills View Community?
Dubai Hills Estate L.L.C, as registered with DLD.
What is the DLD project number of Dubai Hills - Hills View Community?
1398.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error