Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 335Completed122 units

La Fontana Di Trevi لا فونتانا دي تريفي Al Barshaa South Third · Arjan by Triveni Builders & Promoters LimitedAll phases of Arjan Completed 1 June 2011 (DLD) DLD end date Jun 2011 DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.

Completed projects cannot be added to My units.

Completed
Jun 2011
DLD end date Jun 2011
Build time
25 months
Apr 2009 → Jun 2011
Latest sales
815 AED/sqft
6 sales
1 BR rent
63,000 AED/yr
19 leases, 12 months
Developer
1 project
1 completed · 122 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built

28 October 2026
Built
100%
Latest DLD register reading: 100% built on 28 October 2026 (register readings: 3).

DLD has no site-inspection readings for this project in our copy.

Every DLD inspection and every change in the register %, newest first
Date % built Source
5 August 2022 100% DLD register, archived export

Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 5 August 2022, 12 May 2024.

Site timeline

± 6 months

Our imagery reading holds no milestone for this project yet.

Our reading of historical satellite imagery

Registered period and actual build

Registered period
25 monthsActual build
25 months
Start date
30 April 2009
DLD end date
1 June 2011
Completion date
1 June 2011
Completion vs DLD end date
On the date

Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.

Changes in the DLD register

No change to the end date, status or % built across the register exports we hold.

Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.

DLD registration

DLD services ↗
DLD project number
335
Escrow agent
Mashreq Bank PSC
Zoning authority
Dubai Development Authority (DDA)
Master project
Arjan
DLD area
Al Barshaa South Third
Units · villas
122 · 0
Start → DLD end
Apr 2009 → Jun 2011
Registered units1 bed 82 · 2 bed 40; sizes 809–1,177 sqft

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: Freehold residential development located in Mizin (Barsha South Third) consisting of B+G+6 floors and a total of 126 units. The building is being constructed as a concrete structure with external and internal finishes.

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft

No off-plan sales are registered for this project since 2020, so there is no launch price.

Prices are over apartments, the type most sales in this project are.

Registered sales of apartments by bedroom count over the last 24 months, and the median AED/sqft of the latest ready sales (number of sales)
Bedrooms Sales, 24 months Latest median AED/sqft Latest sales
1 BR 13 — —
2 BR 5 — —

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Median AED/sqft by quarter

2020-Q4 → 2026-Q3

Median AED/sqft of registered sales per quarter (apartments). Source: DLD. Grey dashed line: DLD area Al Barshaa South Third, median AED/sqft of ready sales of apartments by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

Rents and gross yield

New Ejari rent contracts for apartments in this project, 12 months to 5 November 2026, against the 12 months before. Fewer than 10 ready sales per bedroom count in those 12 months, so no yield is shown.

Bedrooms Median annual rent New contracts Change on a year earlier
1 BR AED 63,000 19 +8.6%
2 BR AED 82,200 8 +2.8%

New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.

Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.

Mortgage registrations

Home mortgages DLD has registered on units in this project, per quarter, in the 12 quarters to 5 November 2026.

Mortgage registrations on homes per quarter. Source: DLD.

Mortgage registrations in the last 4 quarters (2026-Q1 to 2026-Q4): 4; the amount shows from 5 registrations.

Since the first registration in 2012-Q2: 55 in all.

Counts DLD's mortgage registrations on homes in this project, including pre-registrations on off-plan units and lease-to-own registrations; portfolio and developer mortgages are left out. Amounts are the values DLD registers, shown for 5 registrations or more. A registration says nothing about the lender or the terms.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

Service charges

What owners pay a year in completed buildings of the project’s master community, from their owners’ association budgets. A building’s own charge is set by its own budget.

Apartment buildings’ budgets; villa and townhouse budgets are left out.
16.26 AED/sqft a year
Arjan: median of 33 developments’ owners’ association budgets, 2026

Median AED per sq ft a year of residential owners’ association budgets, each development counted once, in the newest budget year with at least 10 developments. Plots, shared areas and hotel rooms are left out. A budget is not any one owner’s bill.

Source: Dubai Land Department, owners’ association budgets (service charges).

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

The newest 10 of 6 registered sales in the 12 months to 5 November 2026
DateMarketType Size (sqft) Price (AED) AED/sqft
16 September 2026readyApartment · 1 BR 920 750,000 815
1 May 2026readyApartment · 1 BR 837 680,000 812
21 April 2026readyApartment · 2 BR 1,264 1,150,000 910
13 April 2026readyApartment · 1 BR 838 675,000 805
6 March 2026readyApartment · 2 BR 1,194 1,100,000 921
5 January 2026readyApartment · 2 BR 1,194 1,100,000 921
3 November 2025readyApartment · 2 BR 1,627 1,200,000 738
28 October 2025readyApartment · 1 BR 925 755,000 816
24 July 2025readyApartment · 1 BR 348 290,000 833
28 May 2025readyApartment · 2 BR 1,264 1,110,000 878

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

LocationAl Barsha South Third · Dubai Municipality community

Grandiose · 240 mNesto · 280 mViva · 370 mAustralian International School Dubai (AIS Dubai) · 500 mCity Centre Al Barsha · 880 mNord Anglia International School · 960 mSchool · 960 mDubai Miracle Garden · 960 mDubai Butterfly Garden · 1 kmSchool · 1.2 kmSafa Community School · 1.2 kmPark · 1.4 kmProject location© OpenStreetMap contributors · Dubai Municipality · RTA · Makani
Project location Malls and supermarkets Schools and hospitals Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

Metro stationMashreq Metro Station · Red Metro line · 7.3 km
MallCity Centre Al Barsha · 880 m
SupermarketGrandiose · 240 m
HospitalAmerican · 5.4 km
SchoolAustralian International School Dubai (AIS Dubai) · 500 m
ParkDubai Miracle Garden · 960 m

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors · RTA

New homes within 1.5 km

Open projects within 1.5 km of the pin: 36, with 12,011 units and villas.

2022: 1242025: 9772026: 3,5282027: 1,2932028: 2,7012029: 1,437No end date: 1,951

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Al Barsha South Third: 30

Open projects in the same DLD area, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Marquis One 0.3% Dec 2028 1,705 397
The central downtown 10.5% Mar 2028 1,445 365
Samana Imperial Garden 4.2% Dec 2028 1,871 326
One Beverly 72.9% Dec 2026 1,680 287
Ashley Hills 74.1% Mar 2027 1,498 287
Binghatti Hillcrest 60% Dec 2026 2,238 282
Floarea Grande 48.2% Aug 2027 1,656 222
Vincitore Dolce Vita 40% — 1,652 210
Empire Estates 60% Dec 2026 1,717 207
butterfly 7.7% Jan 2029 1,609 198
Enchante By GRID 0% Dec 2028 1,751 161
Parkside Boulevard 51.9% Dec 2027 1,419 128

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Al Barsha South Third

Developer in DLD data Triveni Builders & Promoters Limited · DLD developer no. 207

Projects registered
1
1 completed · 0 under construction · 0 not started
Units delivered
122
0 in the pipeline

Completed a month or more after their DLD end date: 0 of 1 completed projects with both dates. In 1 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Other projects in Arjan

DLD lists 80 projects in the master project Arjan.

Aryene GreensUnder construction · 80.1% · Nov 2022
Vincitore VolareUnder construction · 63.4% · Jun 2025
Elano By ORO24Under construction · 70% · Oct 2025
Gardens 2Under construction · 68.5% · Dec 2025
Samana Mykonos SignatureUnder construction · 86% · Apr 2026
Samana SkyrosUnder construction · 71.3% · Apr 2026
Cavara 42Under construction · 75.8% · May 2026
Kyoto By ORO24Under construction · 17% · Sep 2026
Trinity By KarmaUnder construction · 30.9% · Dec 2026
One BeverlyUnder construction · 72.9% · Dec 2026
Binghatti HillcrestUnder construction · 60% · Dec 2026
Empire EstatesUnder construction · 60% · Dec 2026

Questions about La Fontana Di Trevi

When was La Fontana Di Trevi completed?

La Fontana Di Trevi is recorded as completed on 1 June 2011 (DLD register of 1 November 2026).

Who is the developer of La Fontana Di Trevi?

Triveni Builders & Promoters Limited, as registered with DLD.

What is the DLD project number of La Fontana Di Trevi?

335.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error