Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 1906Completed99 units

Qline (Qpoint phase II) R085 كيولاين ( كيوبوينت فيز 2) R085 Wadi Al Safa 2 · Liwan1 by Al Mazaya Emirates Real Estate Development Owned By Mazaya Alghad One Person Company L.L.CAll phases of Liwan1 Completed 26 October 2017 (DLD) DLD end date Oct 2017 DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.

Completed projects cannot be added to My units.

Completed
Oct 2017
DLD end date Oct 2017
Build time
15 months
Aug 2016 → Oct 2017
Latest sales
—
Fewer than 5 recent sales
Developer
4 projects
4 completed · 482 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built

28 October 2026
Built
100%
Latest DLD register reading: 100% built on 28 October 2026 (register readings: 3). Latest DLD inspection: 100% built on 20 December 2017 (inspections: 2).
Every DLD inspection and every change in the register %, newest first
Date % built Source
20 December 2017 100% DLD inspection
9 August 2017 75.1% DLD inspection

Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 5 August 2022, 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗

Site timeline

± 6 months

Our imagery reading holds no milestone for this project yet.

Our reading of historical satellite imagery

Registered period and actual build

Registered period
15 monthsActual build
15 months
Start date
1 August 2016
DLD end date
26 October 2017
Completion date
26 October 2017
Completion vs DLD end date
On the date

Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.

Changes in the DLD register

No change to the end date, status or % built across the register exports we hold.

Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.

Building permits

1 of 1 buildings

Buildings on the project’s plots: 1, on construction permits: 1, as Dubai Municipality lists them.

Furthest stage reached: Final works.

Work not started
Site works
Foundations
Structure
Masonry
Finishes
Final works
Completed
Buildings
1
1 on construction permits
Permit status
Closed
254180
Issued
18 August 2016
Work start
1 August 2016
Completion
26 October 2017
Consultant · contractor
BEL YOAHAH ARCHITECTURAL & ENGINEERING CONSULTANTS L.L.C · AL SAHEL CONTRACTING CO.(L.L.C)
Buildings by the furthest work stage Dubai Municipality lists
Work stage Buildings
Final works1

Source: Dubai Municipality building permits, export of 26 October 2026. These dates and stages are Dubai Municipality’s records, not DLD’s register.

DLD registration

DLD services ↗
DLD project number
1906
Escrow agent
Mashreq Bank PSC
Zoning authority
Dubai Development Authority (DDA)
Master project
Liwan1
DLD area
Wadi Al Safa 2
Units · villas
99 · 0
Start → DLD end
Aug 2016 → Oct 2017
Registered unitsStudio 9 · 1 bed 72 · 2 bed 18; sizes 816–951 sqft

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: PROJECT CONSISTS OF G+9+R RESIDENTIAL BUILDING LOCATED IN WADI AL SAFA 2. THE APARTMENTS ARE DESIGNED TO HAVE A CONCRETE STRUCTURE AND BLOCK WITH INTERNAL AND EXTERNAL FINISHES.

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft

No off-plan sales are registered for this project since 2020, so there is no launch price.

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

LocationWadi Al Safa 2 · Dubai Municipality community

Park · 130 mShams Al Madina · 350 mSupercare · 440 mSilicon Central · 920 mMUMUSO · 920 mCentro Courtyard 3 · 1.1 kmCentral park · 1.1 kmIndian International School · 1.5 kmProject location© OpenStreetMap contributors · Dubai Municipality · Makani
Project location Malls and supermarkets Schools and hospitals Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

MallSilicon Central · 920 m
SupermarketShams Al Madina · 350 m
HospitalHLG Umar · 2.5 km
SchoolIndian International School · 1.5 km
ParkPark · 130 m
BeachBeach · 4.6 km

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors

New homes within 1.5 km

Open projects within 1.5 km of the pin: 64, with 15,918 units and villas.

2025: 242026: 8122027: 6,2272028: 6,9032029: 1,472No end date: 480

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Wadi Al Safa 2: 23

Open projects in the same DLD area, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Belgravia Gardens 3.1% Sep 2028 1,599 707
Empire Lakeviews 2.1% Jun 2028 1,629 567
Sakura Gardens by HRE 3.6% Jun 2029 1,599 229
Reem by vision 70.4% Dec 2026 1,129 192
Bianca 56.1% Dec 2026 1,317 156
Alma Gardens 50.3% May 2026 1,194 76
Sobha Reserve 75% — — 74
Symbolic Altus 1.3% May 2027 1,295 49
Albero By ORO24 44.8% — — 25
Parkgreen Residences By Alishaan 4.3% Jun 2028 1,243 18
Serra Residence By Wujod 28.8% Dec 2027 — 4
Sunrise Boulevard 5 0% Jul 2010 — 0

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Wadi Al Safa 2

Developer in DLD data Al Mazaya Emirates Real Estate Development Owned By Mazaya Alghad One Person Company L.L.C · DLD developer no. 904

Projects registered
4
4 completed · 0 under construction · 0 not started
Units delivered
482
0 in the pipeline
Median build time
16 months
completed projects measured: 4

Completed a month or more after their DLD end date: 0 of 4 completed projects with both dates. In 4 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Other projects in Liwan1

DLD lists 68 projects in the master project Liwan1.

Alma GardensUnder construction · 50.3% · May 2026
Reem by visionUnder construction · 70.4% · Dec 2026
Symbolic AltusUnder construction · 1.3% · May 2027
Empire LakeviewsUnder construction · 2.1% · Jun 2028
Parkgreen Residences By AlishaanUnder construction · 4.3% · Jun 2028
Albero By ORO24Under construction · 44.8% · —
Sunrise Boulevard 5Pending · 0% · Jul 2010
Viani by MeteoraPending · 0% · Jun 2027
Project 4049, Wadi Al Safa 2Pending · 0% · Mar 2028
Confident PrestonPending · 0% · Apr 2028
ZetaPending · 0% · Nov 2028
Project 4567, Wadi Al Safa 2Pending · 0% · Jul 2029

Questions about Qline (Qpoint phase II) R085

When was Qline (Qpoint phase II) R085 completed?

Qline (Qpoint phase II) R085 is recorded as completed on 26 October 2017 (DLD register of 1 November 2026).

Who is the developer of Qline (Qpoint phase II) R085?

Al Mazaya Emirates Real Estate Development Owned By Mazaya Alghad One Person Company L.L.C, as registered with DLD.

What is the DLD project number of Qline (Qpoint phase II) R085?

1906.