DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 4522Not started142 units

THE BAY interiors by Missoni ذا باي انتيريورز باي ميسوني Palm Deira by Tomorrow World Real Estate Development L.L.CAll phases of Palm Deira DLD status: Not started (DLD register as of 1 November 2026) DLD end date Sep 2029 34 months to go DLD register as of 1 November 2026. The end date is the one registered with DLD, not a handover forecast.

% built
0%
DLD register, 1 November 2026
Registered start
Sep 2026
DLD end date Sep 2029
Latest sales
—
Fewer than 5 recent sales
Developer
4 projects
0 completed · 0 units delivered

Completion

DLD status: Not started. 0% built, DLD end date 30 September 2029. DLD Project Status shows inspection reports once works begin.

DLD register readings
Date % built DLD end dateDLD status
28 October 2026 0% 30 September 2029Not started

Source: DLD projects register, export of 1 November 2026.

Inspection photos and reports

DLD’s Project Status service (Mashrooi) shows inspection details and site photos. Look the project up by its number.

CraneScore links to DLD and does not copy or host its photos or reports.

DLD registration

DLD services ↗
DLD project number
4522
Escrow agent
The National Bank of Fujairah P S C
Zoning authority
Trakhees
Master project
Palm Deira
DLD area
Palm Deira
Units · villas
142 · 0
Start → DLD end
Sep 2026 → Sep 2029
Registered units2 bed 104 · 3 bed 26 · 4 bed 2; sizes 1,008–1,181 sqft

Also registered: shops and showrooms 10.

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: G+2P+14+Roof Mix use building

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

LocationNakhlat Deira · Dubai Municipality community

Al Madina · 1.1 kmGold Souq Metro Station · 1.2 kmPark · 1.3 kmBeach · 1.3 kmAl Sadaqa Grocery · 1.4 kmAlhayat Grocery · 1.4 kmProject location© OpenStreetMap contributors · Dubai Municipality · RTA · Makani
Project location Metro and tram Malls and supermarkets Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

Metro stationGold Souq Metro Station · Green Metro line · 1.2 km
MallNaif Souq · 1.8 km
SupermarketAl Madina · 1.1 km
HospitalBelhoul Speciality Hospital · 1.9 km
SchoolAl Wahidah Boys' School for Cycle2 and Secondary Education. C2 & C3 · 2.5 km
ParkPark · 1.3 km
BeachBeach · 1.3 km

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors · RTA

New homes within 1.5 km

Open projects within 1.5 km of the pin: 65, with 5,775 units and villas.

2025: 1202026: 8272027: 2,6512028: 1,6432029: 3862031: 0No end date: 148

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Nakhlat Deira: 133

Open projects in the same DLD area with a DLD end year from 2028 to 2030, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Hado By Beyond 0% Jun 2029 3,152 629
Ellington Sands I 0.4% Dec 2028 2,761 434
Ellington Sands Ii 0.4% Dec 2028 2,822 428
Bay Grove Residences C - Dubai Islands 7.3% Apr 2028 2,379 369
Bay Grove Residences, Dubai Islands 12.3% Mar 2028 2,282 307
Bay Grove Residences D - Dubai Islands 3.7% Sep 2028 2,637 258
Flora Isle 11.3% Jan 2028 2,839 242
Bay Grove Residences B - Dubai Islands 7.6% Sep 2028 — 242
Silena Residences 3.8% May 2028 3,484 123
Ocean Bay by Samana Developers 3.2% Jun 2028 2,256 114
Sunset Bay Grand By Imtiaz 16.3% Feb 2028 2,321 83
Seacliff by Imtiaz 7.7% Aug 2028 2,397 80

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Nakhlat Deira

Developer in DLD data Tomorrow World Real Estate Development L.L.C · DLD developer no. 1977

Projects registered
4
0 completed · 2 under construction · 2 not started
Units delivered
0
449 in the pipeline
Past the DLD end date
1
of 2 under construction with a DLD end date

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error