Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Our location listMadinat Al Mataar

Azizi Venice 16 of 16 phases not yet completed · 20,712 units · 10,953 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026

Azizi Venice has 16 projects in the Dubai Land Department projects register as of 1 November 2026: 16 not yet completed, with 20,712 units and villas. By DLD status: Under construction 14 · Not started 2. Under construction and past the DLD end date: 7.

Phases
16
0 completed
Not yet completed
16
14 under construction
Units not yet completed
20,712
units and villas
Sales, 24 mo
10,953
registered with DLD

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Map of the phasesThe map shows 16 of the 16 phases: those with a map pin. Pins mark approximate locations.

Azizi Venice 14 · Under construction · Project locationAzizi Venice 6 · Under construction · Project locationAzizi Venice 7 · Under construction · Project locationAzizi Venice 15 · Not started · Project locationazizi venice 13 · Under construction · Project locationAzizi Venice 10 · Under construction · Project locationazizi venice 12 · Under construction · Project locationAzizi Venice 11 · Under construction · Project locationAzizi Venice 9 · Under construction · Project locationAzizi Venice 8 · Under construction · Project locationAzizi Venice 16 · Not started · Project locationAzizi Venice 5 · Under construction · Project locationAzizi Venice 2 · Under construction · Project locationAzizi Venice 4 · Under construction · Project locationAzizi Venice 3 · Under construction · Project locationAzizi Venice 1 · Under construction · Project locationDubai Municipality · Makani
Under construction Not started

Madinat Al Mataar (DM community)

Phases (16)Ordered by registered sales over 24 months

Phases (16)
ProjectDLD status Built DLD end date / completion To DLD end date Units Sales, 24 mo Since launch
Azizi Venice 14Under construction 30.3% May 2026 5 months past it 5 months past it 3,438 2,546 +6.3%
Azizi Venice 6Under construction 11.6% Dec 2027 13 months to go 13 months to go 2,965 1,302 +3.4%
Azizi Venice 7Under construction 29.2% Jan 2026 9 months past it 9 months past it 2,276 1,180 +17.6%
Azizi Venice 15Not started 0% May 2027 6 months to go 6 months to go 1,855 904 +6.4%
azizi venice 13Under construction 45.9% Sep 2027 10 months to go 10 months to go 1,888 797 +4.4%
Azizi Venice 10Under construction 36.3% — — 1,263 776 +8.9%
azizi venice 12Under construction 21.6% Sep 2027 10 months to go 10 months to go 1,428 753 +2.1%
Azizi Venice 11Under construction 25.9% Aug 2027 9 months to go 9 months to go 1,094 696 +7.2%
Azizi Venice 9Under construction 54% — — 778 428 +8.4%
Azizi Venice 8Under construction 53% — — 778 372 -2.7%
Azizi Venice 16Not started 0% Jun 2027 7 months to go 7 months to go 1,055 310 -1%
Azizi Venice 5Under construction 63.5% Oct 2025 12 months past it 12 months past it 484 309 -2.8%
Azizi Venice 2Under construction 57.2% Dec 2025 10 months past it 10 months past it 526 264 —
Azizi Venice 4Under construction 62.2% Dec 2025 10 months past it 10 months past it 389 167 +3.1%
Azizi Venice 3Under construction 76% Dec 2025 10 months past it 10 months past it 352 83 -1.1%
Azizi Venice 1Under construction 67.4% Dec 2025 10 months past it 10 months past it 143 66 —

Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Units not yet completed, by DLD end year

16 phases
2025: 1,8942026: 5,7142027: 10,285No end date: 2,819

Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.

More on Azizi Venice

Own a unit in one of these phases? Track it free

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology