Azizi Venice 16 of 16 phases not yet completed · 20,712 units · 10,953 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026
Azizi Venice has 16 projects in the Dubai Land Department projects register as of 1 November 2026: 16 not yet completed, with 20,712 units and villas. By DLD status: Under construction 14 · Not started 2. Under construction and past the DLD end date: 7.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Map of the phasesThe map shows 16 of the 16 phases: those with a map pin. Pins mark approximate locations.
Madinat Al Mataar (DM community)
Phases (16)Ordered by registered sales over 24 months
| Project | DLD status | Built | DLD end date / completion | To DLD end date | Units | Sales, 24 mo | Since launch |
|---|---|---|---|---|---|---|---|
| Azizi Venice 14 | Under construction | 30.3% | May 2026 5 months past it | 5 months past it | 3,438 | 2,546 | +6.3% |
| Azizi Venice 6 | Under construction | 11.6% | Dec 2027 13 months to go | 13 months to go | 2,965 | 1,302 | +3.4% |
| Azizi Venice 7 | Under construction | 29.2% | Jan 2026 9 months past it | 9 months past it | 2,276 | 1,180 | +17.6% |
| Azizi Venice 15 | Not started | 0% | May 2027 6 months to go | 6 months to go | 1,855 | 904 | +6.4% |
| azizi venice 13 | Under construction | 45.9% | Sep 2027 10 months to go | 10 months to go | 1,888 | 797 | +4.4% |
| Azizi Venice 10 | Under construction | 36.3% | — | — | 1,263 | 776 | +8.9% |
| azizi venice 12 | Under construction | 21.6% | Sep 2027 10 months to go | 10 months to go | 1,428 | 753 | +2.1% |
| Azizi Venice 11 | Under construction | 25.9% | Aug 2027 9 months to go | 9 months to go | 1,094 | 696 | +7.2% |
| Azizi Venice 9 | Under construction | 54% | — | — | 778 | 428 | +8.4% |
| Azizi Venice 8 | Under construction | 53% | — | — | 778 | 372 | -2.7% |
| Azizi Venice 16 | Not started | 0% | Jun 2027 7 months to go | 7 months to go | 1,055 | 310 | -1% |
| Azizi Venice 5 | Under construction | 63.5% | Oct 2025 12 months past it | 12 months past it | 484 | 309 | -2.8% |
| Azizi Venice 2 | Under construction | 57.2% | Dec 2025 10 months past it | 10 months past it | 526 | 264 | — |
| Azizi Venice 4 | Under construction | 62.2% | Dec 2025 10 months past it | 10 months past it | 389 | 167 | +3.1% |
| Azizi Venice 3 | Under construction | 76% | Dec 2025 10 months past it | 10 months past it | 352 | 83 | -1.1% |
| Azizi Venice 1 | Under construction | 67.4% | Dec 2025 10 months past it | 10 months past it | 143 | 66 | — |
Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Units not yet completed, by DLD end year
16 phases| DLD end year | Projects | Units |
|---|---|---|
| 2025 | 5 | 1,894 |
| 2026 | 2 | 5,714 |
| 2027 | 6 | 10,285 |
| No end date | 3 | 2,819 |
Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.
More on Azizi Venice
Own a unit in one of these phases? Track it free
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology