Dubai Creek Harbour 17 of 48 phases not yet completed · 7,382 units · 7,369 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026
Dubai Creek Harbour has 48 projects in the Dubai Land Department projects register as of 1 November 2026: 17 not yet completed, with 7,382 units and villas. By DLD status: Under construction 16 · Not started 1 · Completed 31.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Map of the phasesThe map shows 48 of the 48 phases: those with a map pin. Pins mark approximate locations.
Al Kheeran First (DM community)
Phases (48)Ordered by registered sales over 24 months
| Project | DLD status | Built | DLD end date / completion | To DLD end date | Units | Sales, 24 mo | Since launch |
|---|---|---|---|---|---|---|---|
| Creek Bay | Under construction | 0.6% | Apr 2030 41 months to go | 41 months to go | 766 | 703 | +1.8% |
| Creek Haven | Under construction | 0.9% | Mar 2030 40 months to go | 40 months to go | 594 | 473 | +2.3% |
| Montiva | Under construction | 5.9% | Sep 2029 34 months to go | 34 months to go | 475 | 466 | -3% |
| Lyvia by Palace | Under construction | 4.8% | Jul 2029 32 months to go | 32 months to go | 481 | 462 | -2.7% |
| Albero | Under construction | 11% | Sep 2029 34 months to go | 34 months to go | 479 | 460 | -4.5% |
| Altan | Under construction | 11.1% | Jul 2029 32 months to go | 32 months to go | 479 | 452 | -4.7% |
| Valia | Not started | 0% | Aug 2030 45 months to go | 45 months to go | 492 | 439 | — |
| Silva | Under construction | 10.2% | Sep 2029 34 months to go | 34 months to go | 437 | 431 | -2.1% |
| Creek Beach - Canopy - Moor | Completed | 100% | Nov 2025 | — | 444 | 223 | -1.5% |
| The Grand | Completed | 100% | Oct 2022 | — | 574 | 205 | — |
| The Cove ll | Completed | 100% | May 2026 | — | 806 | 178 | +14.4% |
| Creek Beach - Savanna-Cedar-Mangrove | Completed | 100% | Nov 2025 | — | 595 | 162 | +7.2% |
| The Dubai Creek Residences | Completed | 100% | Mar 2018 | — | 924 | 152 | — |
| Creek Palace | Completed | 100% | Mar 2026 | — | 337 | 140 | +46.9% |
| Creek Rise | Completed | 100% | Jun 2022 | — | 547 | 129 | — |
| Creek Edge | Completed | 100% | Sep 2023 | — | 564 | 124 | — |
| Palace Residences - North | Completed | 100% | Sep 2025 | — | 340 | 123 | +26.5% |
| Island Park I | Completed | 100% | Feb 2025 | — | 160 | 110 | +46.4% |
| Altus | Under construction | 64.2% | Jan 2029 26 months to go | 26 months to go | 283 | 106 | +1.5% |
| Harbour Gate | Completed | 100% | Jan 2022 | — | 517 | 105 | — |
| Harbour Views | Completed | 100% | Apr 2020 | — | 784 | 101 | — |
| Creekside 18 | Completed | 100% | May 2020 | — | 506 | 100 | — |
| Creek Horizon | Completed | 100% | Sep 2020 | — | 559 | 100 | — |
| Palace Residences - Dubai Creek Harbour | Completed | 100% | Dec 2022 | — | 592 | 100 | — |
| Island Park II | Completed | 100% | Feb 2025 | — | 160 | 97 | +43% |
| Creek Waters 2 | Under construction | 81.8% | Dec 2027 13 months to go | 13 months to go | 455 | 91 | -3.3% |
| Creek Crescent | Completed | 100% | Mar 2023 | — | 230 | 90 | +31.7% |
| Creek Beach - Lotus | Completed | 100% | Sep 2025 | — | 270 | 90 | +40.5% |
| Creek Beach - Grove | Completed | 100% | Jun 2023 | — | 269 | 89 | +36.2% |
| Creek Waters | Under construction | 81.1% | Sep 2027 10 months to go | 10 months to go | 453 | 85 | +3.8% |
| Creek Gate | Completed | 100% | Nov 2021 | — | 498 | 83 | — |
| Creek Beach - Orchid | Completed | 100% | Sep 2025 | — | 208 | 80 | +22.7% |
| Creek Beach - Rosewater | Completed | 100% | Mar 2023 | — | 211 | 72 | +19.3% |
| Palace Residences Creek Blue | Under construction | 20.5% | Mar 2029 28 months to go | 28 months to go | 512 | 71 | -0.5% |
| 17 Icon Bay | Completed | 100% | Nov 2022 | — | 383 | 63 | — |
| Address Residences l Dubai Creek Harbour | Under construction | 26.4% | Jan 2029 26 months to go | 26 months to go | 326 | 60 | +0.8% |
| Creek Beach - VIDA Residences | Completed | 100% | Apr 2023 | — | 233 | 60 | — |
| The Cove | Completed | 100% | Nov 2021 | — | 291 | 57 | — |
| Creek Beach - Bayshore | Completed | 100% | Oct 2022 | — | 305 | 53 | — |
| Arlo | Under construction | 35.4% | — | — | 434 | 31 | +1.8% |
| Creek Beach - Surf | Completed | 100% | Mar 2023 | — | 173 | 28 | — |
| Valo | Under construction | 66.1% | — | — | 291 | 26 | — |
| Creek Beach - Summer | Completed | 100% | Mar 2023 | — | 305 | 26 | — |
| Creek Beach - Sunset | Completed | 100% | Oct 2022 | — | 151 | 21 | — |
| Oria | Under construction | 71.1% | — | — | 163 | 20 | — |
| Creek Beach - Breeze | Completed | 100% | Oct 2022 | — | 202 | 17 | — |
| Aeon | Under construction | 90% | — | — | 262 | 15 | — |
| Address Harbour Point | Completed | 100% | Jan 2023 | — | 813 | 0 | — |
Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Units not yet completed, by DLD end year
17 phases| DLD end year | Projects | Units |
|---|---|---|
| 2027 | 2 | 908 |
| 2029 | 8 | 3,472 |
| 2030 | 3 | 1,852 |
| No end date | 4 | 1,150 |
Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.
More on Dubai Creek Harbour
Own a unit in one of these phases? Track it free
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology