Dubai Harbour 13 of 21 phases not yet completed · 6,458 units · 2,466 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026
Dubai Harbour has 21 projects in the Dubai Land Department projects register as of 1 November 2026: 13 not yet completed, with 6,458 units and villas. By DLD status: Under construction 11 · Completed 8 · Not started 2.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Map of the phasesThe map shows 21 of the 21 phases: those with a map pin. Pins mark approximate locations.
Marsa Dubai (DM community)
Phases (21)Ordered by registered sales over 24 months
| Project | DLD status | Built | DLD end date / completion | To DLD end date | Units | Sales, 24 mo | Since launch |
|---|---|---|---|---|---|---|---|
| W Residences at Dubai Harbour | Under construction | 4% | Dec 2028 25 months to go | 25 months to go | 494 | 337 | +11.4% |
| THE BRISTOL Emaar Beachfront | Under construction | 5.8% | Sep 2029 34 months to go | 34 months to go | 229 | 227 | — |
| Sobha Seahaven Tower B & C | Under construction | 40.2% | Oct 2028 23 months to go | 23 months to go | 451 | 162 | +3.1% |
| Dubai Harbour Residences (Area 1) | Under construction | 30.3% | Jan 2028 14 months to go | 14 months to go | 217 | 161 | +2.2% |
| Grand Bleu Tower interiors by Elie Saab | Completed | 100% | May 2023 | — | 639 | 158 | — |
| Palace Beach Residence | Completed | 100% | Oct 2025 | — | 552 | 144 | +43% |
| Damac Bay | Under construction | 33.8% | Jan 2027 2 months to go | 2 months to go | 1,087 | 142 | -13.4% |
| Seapoint | Under construction | 36.8% | Mar 2028 16 months to go | 16 months to go | 674 | 138 | +0.7% |
| Damac Bay 2 | Under construction | 30.3% | — | — | 646 | 137 | +1.9% |
| Beach Mansion | Completed | 100% | Nov 2025 | — | 495 | 127 | +24.3% |
| Dubai Harbour Residences (Area 3) | Under construction | 34.8% | Jan 2028 14 months to go | 14 months to go | 159 | 125 | — |
| Marina Vista | Completed | 100% | Mar 2023 | — | 625 | 90 | — |
| The Residences at the Dubai Beach Edition | Not started | 0.2% | Nov 2029 36 months to go | 36 months to go | 169 | 82 | -0.4% |
| Beach Vista | Completed | 100% | Jan 2022 | — | 466 | 74 | — |
| Sunrise Bay | Completed | 100% | Oct 2021 | — | 461 | 74 | — |
| Address The Bay | Under construction | 70.1% | Dec 2026 1 month to go | 1 month to go | 448 | 72 | +34% |
| Bayview | Under construction | 63% | Jul 2028 20 months to go | 20 months to go | 690 | 63 | -2.4% |
| Sobha Seahaven Tower A | Under construction | 37% | Apr 2028 17 months to go | 17 months to go | 333 | 61 | +2.7% |
| Beach Isle | Completed | 100% | Apr 2023 | — | 397 | 54 | +54.3% |
| Beachgate by Address | Completed | 100% | Sep 2026 | — | 252 | 38 | -1.4% |
| Palace by the Beach | Not started | 0% | Nov 2031 60 months to go | 60 months to go | 861 | 0 | — |
Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Units not yet completed, by DLD end year
13 phases| DLD end year | Projects | Units |
|---|---|---|
| 2026 | 1 | 448 |
| 2027 | 1 | 1,087 |
| 2028 | 7 | 3,018 |
| 2029 | 2 | 398 |
| 2031 | 1 | 861 |
| No end date | 1 | 646 |
Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.
More on Dubai Harbour
Own a unit in one of these phases? Track it free
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology