DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD master projectMadinat Dubai Al Melaheyah

Dubai Maritime City 27 of 29 phases not yet completed · 12,252 units · 6,216 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026

Dubai Maritime City has 29 projects in the Dubai Land Department projects register as of 1 November 2026: 27 not yet completed, with 12,252 units and villas. By DLD status: Not started 7 · Under construction 19 · Completed 2 · Pending 1. Under construction and past the DLD end date: 1.

Phases
29
2 completed
Not yet completed
27
19 under construction
Units not yet completed
12,252
units and villas
Sales, 24 mo
6,216
registered with DLD

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Map of the phasesThe map shows 29 of the 29 phases: those with a map pin. Pins mark approximate locations.

Breez by Danube · Not started / Pending · Project locationChelsea Residences 2 By Damac · Under construction · Project locationFranck Muller Yachting · Not started / Pending · Project locationOrise · Under construction · Project locationChelsea Residences By Damac · Under construction · Project locationSaria · Under construction · Project locationKanyon By Beyond · Not started / Pending · Project locationTalea · Not started / Pending · Project locationSensia · Under construction · Project locationThe Mural · Under construction · Project locationLiv Maritime · Under construction · Project locationSoulever' By Beyond · Not started / Pending · Project locationThe Pier · Under construction · Project locationOceanz 2 By Danube · Under construction · Project locationRiva Residence · Completed · Project locationMar Casa · Under construction · Project locationThe Anwa By Omniyat · Completed · Project locationAria By Beyond · Under construction · Project locationOceanz 1 By Danube · Under construction · Project locationPrestige One Residences · Not started / Pending · Project locationHarbour Lights · Under construction · Project locationNautica One · Under construction · Project locationOceanz 3 By Danube · Under construction · Project locationIl Vento · Under construction · Project locationCoral Reef · Under construction · Project locationNautica Two · Under construction · Project location31 Above By Beyond · Under construction · Project locationShahrukhz Residences by Danube · Not started / Pending · Project locationProject 4419, Madinat Dubai Almelaheyah · Not started / Pending · Project locationDubai Municipality · Makani
Under construction Not started / Pending Completed

Madinat Dubai Al Melaheyah (DM community)

Phases (29)Ordered by registered sales over 24 months

Phases (29)
ProjectDLD status Built DLD end date / completion To DLD end date Units Sales, 24 mo Since launch
Breez by DanubeNot started 0.1% Jun 2029 31 months to go 31 months to go 1,199 945 +1.4%
Chelsea Residences 2 By DamacUnder construction 5.4% Dec 2029 37 months to go 37 months to go 958 877 +0.2%
Franck Muller YachtingNot started 0% Jul 2028 20 months to go 20 months to go 585 566 -0.7%
OriseUnder construction 17.6% Nov 2027 12 months to go 12 months to go 534 530 —
Chelsea Residences By DamacUnder construction 5.2% Dec 2029 37 months to go 37 months to go 703 396 +4.8%
SariaUnder construction 31% Oct 2027 11 months to go 11 months to go 372 361 —
Kanyon By BeyondNot started 0% Sep 2028 22 months to go 22 months to go 412 340 -5.1%
TaleaNot started 0% Jun 2028 19 months to go 19 months to go 354 329 -1.7%
SensiaUnder construction 17.5% Mar 2029 28 months to go 28 months to go 276 272 —
The MuralUnder construction 16.6% Jul 2028 20 months to go 20 months to go 268 269 —
Liv MaritimeUnder construction 28.1% Dec 2028 25 months to go 25 months to go 258 247 +28.5%
Soulever' By BeyondNot started 0% Dec 2028 25 months to go 25 months to go 517 233 +0.8%
The PierUnder construction 48.4% Dec 2026 1 month to go 1 month to go 282 184 +0.4%
Oceanz 2 By DanubeUnder construction 42% — — 781 123 -3%
Riva ResidenceCompleted 100% Dec 2025 — 155 92 —
Mar CasaUnder construction 56.5% Oct 2026 This month This month 585 82 +7.4%
The Anwa By OmniyatCompleted 100% Nov 2021 — 233 74 —
Aria By BeyondUnder construction 84.9% Jan 2026 9 months past it 9 months past it 192 64 +7.9%
Oceanz 1 By DanubeUnder construction 50% — — 538 51 +3.3%
Prestige One ResidencesNot started 0.1% Dec 2029 37 months to go 37 months to go 220 47 -14%
Harbour LightsUnder construction 64.3% May 2027 6 months to go 6 months to go 297 38 —
Nautica OneUnder construction 85.2% — — 328 33 +6.1%
Oceanz 3 By DanubeUnder construction 20.6% — — 393 21 +12.3%
Il VentoUnder construction 1.2% Sep 2029 34 months to go 34 months to go 331 16 —
Coral ReefUnder construction 32.9% — — 280 13 —
Nautica TwoUnder construction 85.5% — — 328 13 +5.4%
31 Above By BeyondUnder construction 0.5% Dec 2028 25 months to go 25 months to go 118 0 —
Shahrukhz Residences by DanubeNot started 0% Jun 2030 43 months to go 43 months to go 1,143 0 —
Project 4419, Madinat Dubai AlmelaheyahPending 0% Sep 2029 34 months to go 34 months to go 0 0 —

Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Units not yet completed, by DLD end year

27 phases
2026: 1,0592027: 1,2032028: 2,5122029: 3,6872030: 1,143No end date: 2,648

Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.

More on Dubai Maritime City

Own a unit in one of these phases? Track it free

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology