DLD master projectMadinat Dubai Al Melaheyah
Dubai Maritime City 27 of 29 phases not yet completed · 12,252 units · 6,216 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026
Dubai Maritime City has 29 projects in the Dubai Land Department projects register as of 1 November 2026: 27 not yet completed, with 12,252 units and villas. By DLD status: Not started 7 · Under construction 19 · Completed 2 · Pending 1. Under construction and past the DLD end date: 1.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Map of the phasesThe map shows 29 of the 29 phases: those with a map pin. Pins mark approximate locations.
Madinat Dubai Al Melaheyah (DM community)
Phases (29)Ordered by registered sales over 24 months
| Project | DLD status | Built | DLD end date / completion | To DLD end date | Units | Sales, 24 mo | Since launch |
|---|---|---|---|---|---|---|---|
| Breez by Danube | Not started | 0.1% | Jun 2029 31 months to go | 31 months to go | 1,199 | 945 | +1.4% |
| Chelsea Residences 2 By Damac | Under construction | 5.4% | Dec 2029 37 months to go | 37 months to go | 958 | 877 | +0.2% |
| Franck Muller Yachting | Not started | 0% | Jul 2028 20 months to go | 20 months to go | 585 | 566 | -0.7% |
| Orise | Under construction | 17.6% | Nov 2027 12 months to go | 12 months to go | 534 | 530 | — |
| Chelsea Residences By Damac | Under construction | 5.2% | Dec 2029 37 months to go | 37 months to go | 703 | 396 | +4.8% |
| Saria | Under construction | 31% | Oct 2027 11 months to go | 11 months to go | 372 | 361 | — |
| Kanyon By Beyond | Not started | 0% | Sep 2028 22 months to go | 22 months to go | 412 | 340 | -5.1% |
| Talea | Not started | 0% | Jun 2028 19 months to go | 19 months to go | 354 | 329 | -1.7% |
| Sensia | Under construction | 17.5% | Mar 2029 28 months to go | 28 months to go | 276 | 272 | — |
| The Mural | Under construction | 16.6% | Jul 2028 20 months to go | 20 months to go | 268 | 269 | — |
| Liv Maritime | Under construction | 28.1% | Dec 2028 25 months to go | 25 months to go | 258 | 247 | +28.5% |
| Soulever' By Beyond | Not started | 0% | Dec 2028 25 months to go | 25 months to go | 517 | 233 | +0.8% |
| The Pier | Under construction | 48.4% | Dec 2026 1 month to go | 1 month to go | 282 | 184 | +0.4% |
| Oceanz 2 By Danube | Under construction | 42% | — | — | 781 | 123 | -3% |
| Riva Residence | Completed | 100% | Dec 2025 | — | 155 | 92 | — |
| Mar Casa | Under construction | 56.5% | Oct 2026 This month | This month | 585 | 82 | +7.4% |
| The Anwa By Omniyat | Completed | 100% | Nov 2021 | — | 233 | 74 | — |
| Aria By Beyond | Under construction | 84.9% | Jan 2026 9 months past it | 9 months past it | 192 | 64 | +7.9% |
| Oceanz 1 By Danube | Under construction | 50% | — | — | 538 | 51 | +3.3% |
| Prestige One Residences | Not started | 0.1% | Dec 2029 37 months to go | 37 months to go | 220 | 47 | -14% |
| Harbour Lights | Under construction | 64.3% | May 2027 6 months to go | 6 months to go | 297 | 38 | — |
| Nautica One | Under construction | 85.2% | — | — | 328 | 33 | +6.1% |
| Oceanz 3 By Danube | Under construction | 20.6% | — | — | 393 | 21 | +12.3% |
| Il Vento | Under construction | 1.2% | Sep 2029 34 months to go | 34 months to go | 331 | 16 | — |
| Coral Reef | Under construction | 32.9% | — | — | 280 | 13 | — |
| Nautica Two | Under construction | 85.5% | — | — | 328 | 13 | +5.4% |
| 31 Above By Beyond | Under construction | 0.5% | Dec 2028 25 months to go | 25 months to go | 118 | 0 | — |
| Shahrukhz Residences by Danube | Not started | 0% | Jun 2030 43 months to go | 43 months to go | 1,143 | 0 | — |
| Project 4419, Madinat Dubai Almelaheyah | Pending | 0% | Sep 2029 34 months to go | 34 months to go | 0 | 0 | — |
Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Units not yet completed, by DLD end year
27 phases| DLD end year | Projects | Units |
|---|---|---|
| 2026 | 3 | 1,059 |
| 2027 | 3 | 1,203 |
| 2028 | 7 | 2,512 |
| 2029 | 7 | 3,687 |
| 2030 | 1 | 1,143 |
| No end date | 6 | 2,648 |
Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.
More on Dubai Maritime City
Own a unit in one of these phases? Track it free
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology