DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD master projectAl Wasl

Dubai Water Canal 12 of 19 phases not yet completed · 2,335 units · 1,528 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026

Dubai Water Canal has 19 projects in the Dubai Land Department projects register as of 1 November 2026: 12 not yet completed, with 2,335 units and villas. By DLD status: Under construction 11 · Completed 7 · Not started 1. Under construction and past the DLD end date: 4.

Phases
19
7 completed
Not yet completed
12
11 under construction
Units not yet completed
2,335
units and villas
Sales, 24 mo
1,528
registered with DLD

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Map of the phasesThe map shows 19 of the 19 phases: those with a map pin. Pins mark approximate locations.

Damac City 2 · Under construction · Project locationEden House The Park · Under construction · Approximate project locationCanal Front Residences-CF7 & CF8 & CF9 · Completed · Project locationDamac City · Under construction · Project locationCanal Front Residences-CF3&CF4 · Completed · Project locationCanal Front Residences-CF5&CF6 · Completed · Project locationEden House The Canal · Completed · Project locationMuraba Veil · Under construction · Project locationCanal Front Residences CF1 & CF2 · Completed · Project locationCavalli Couture · Under construction · Project locationCasa Ahs · Under construction · Project locationCasa Canal · Under construction · Project locationOne Canal · Under construction · Project locationPrivate Residences Dubai · Completed · Project locationMr. C Residences Jumeirah · Completed · Project locationThe Rings · Under construction · Project locationThe Melgrano · Under construction · Project locationSea Mirror Residences · Under construction · Project locationAmali Residences · Not started · Project locationDubai Municipality · Makani
Under construction Not started Completed Approximate project locations

Al Wasl (DM community)Jumeira Second (DM community)

Phases (19)Ordered by registered sales over 24 months

Phases (19)
ProjectDLD status Built DLD end date / completion To DLD end date Units Sales, 24 mo Since launch
Damac City 2Under construction 5.7% — — 731 584 -0.5%
Eden House The ParkUnder construction 63.6% Feb 2027 3 months to go 3 months to go 466 317 -9.6%
Canal Front Residences-CF7 & CF8 & CF9Completed 100% Dec 2024 — 374 168 +44.4%
Damac CityUnder construction 72.8% Dec 2025 10 months past it 10 months past it 511 118 +4%
Canal Front Residences-CF3&CF4Completed 100% Jun 2024 — 105 76 +62.2%
Canal Front Residences-CF5&CF6Completed 100% Sep 2024 — 165 73 +39%
Eden House The CanalCompleted 100% Dec 2025 — 100 58 —
Muraba VeilUnder construction 7.6% Dec 2028 25 months to go 25 months to go 135 39 —
Canal Front Residences CF1 & CF2Completed 100% Mar 2024 — 154 29 +33.6%
Cavalli CoutureUnder construction 19.7% May 2025 17 months past it 17 months past it 95 17 +22.7%
Casa AhsUnder construction 16.1% May 2027 6 months to go 6 months to go 32 14 —
Casa CanalUnder construction 38.3% — — 68 12 —
One CanalUnder construction 87.7% May 2025 17 months past it 17 months past it 43 8 —
Private Residences DubaiCompleted 100% Sep 2022 — 30 5 —
Mr. C Residences JumeirahCompleted 100% Jan 2024 — 27 5 —
The RingsUnder construction 35.1% Dec 2025 10 months past it 10 months past it 13 4 —
The MelgranoUnder construction 42.8% Dec 2026 1 month to go 1 month to go 14 1 —
Sea Mirror ResidencesUnder construction 10.4% Dec 2027 13 months to go 13 months to go 19 0 —
Amali ResidencesNot started 0% Dec 2030 49 months to go 49 months to go 208 0 —

Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Units not yet completed, by DLD end year

12 phases
2025: 6622026: 142027: 5172028: 1352030: 208No end date: 799

Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.

More on Dubai Water Canal

Own a unit in one of these phases? Track it free

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology