DLD master projectAl Wasl
Dubai Water Canal 12 of 19 phases not yet completed · 2,335 units · 1,528 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026
Dubai Water Canal has 19 projects in the Dubai Land Department projects register as of 1 November 2026: 12 not yet completed, with 2,335 units and villas. By DLD status: Under construction 11 · Completed 7 · Not started 1. Under construction and past the DLD end date: 4.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Map of the phasesThe map shows 19 of the 19 phases: those with a map pin. Pins mark approximate locations.
Al Wasl (DM community)Jumeira Second (DM community)
Phases (19)Ordered by registered sales over 24 months
| Project | DLD status | Built | DLD end date / completion | To DLD end date | Units | Sales, 24 mo | Since launch |
|---|---|---|---|---|---|---|---|
| Damac City 2 | Under construction | 5.7% | — | — | 731 | 584 | -0.5% |
| Eden House The Park | Under construction | 63.6% | Feb 2027 3 months to go | 3 months to go | 466 | 317 | -9.6% |
| Canal Front Residences-CF7 & CF8 & CF9 | Completed | 100% | Dec 2024 | — | 374 | 168 | +44.4% |
| Damac City | Under construction | 72.8% | Dec 2025 10 months past it | 10 months past it | 511 | 118 | +4% |
| Canal Front Residences-CF3&CF4 | Completed | 100% | Jun 2024 | — | 105 | 76 | +62.2% |
| Canal Front Residences-CF5&CF6 | Completed | 100% | Sep 2024 | — | 165 | 73 | +39% |
| Eden House The Canal | Completed | 100% | Dec 2025 | — | 100 | 58 | — |
| Muraba Veil | Under construction | 7.6% | Dec 2028 25 months to go | 25 months to go | 135 | 39 | — |
| Canal Front Residences CF1 & CF2 | Completed | 100% | Mar 2024 | — | 154 | 29 | +33.6% |
| Cavalli Couture | Under construction | 19.7% | May 2025 17 months past it | 17 months past it | 95 | 17 | +22.7% |
| Casa Ahs | Under construction | 16.1% | May 2027 6 months to go | 6 months to go | 32 | 14 | — |
| Casa Canal | Under construction | 38.3% | — | — | 68 | 12 | — |
| One Canal | Under construction | 87.7% | May 2025 17 months past it | 17 months past it | 43 | 8 | — |
| Private Residences Dubai | Completed | 100% | Sep 2022 | — | 30 | 5 | — |
| Mr. C Residences Jumeirah | Completed | 100% | Jan 2024 | — | 27 | 5 | — |
| The Rings | Under construction | 35.1% | Dec 2025 10 months past it | 10 months past it | 13 | 4 | — |
| The Melgrano | Under construction | 42.8% | Dec 2026 1 month to go | 1 month to go | 14 | 1 | — |
| Sea Mirror Residences | Under construction | 10.4% | Dec 2027 13 months to go | 13 months to go | 19 | 0 | — |
| Amali Residences | Not started | 0% | Dec 2030 49 months to go | 49 months to go | 208 | 0 | — |
Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Units not yet completed, by DLD end year
12 phases| DLD end year | Projects | Units |
|---|---|---|
| 2025 | 4 | 662 |
| 2026 | 1 | 14 |
| 2027 | 3 | 517 |
| 2028 | 1 | 135 |
| 2030 | 1 | 208 |
| No end date | 2 | 799 |
Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.
More on Dubai Water Canal
Own a unit in one of these phases? Track it free
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology