Jaddaf Waterfront 16 of 29 phases not yet completed · 3,182 units · 1,613 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026
Jaddaf Waterfront has 29 projects in the Dubai Land Department projects register as of 1 November 2026: 16 not yet completed, with 3,182 units and villas. By DLD status: Under construction 14 · Completed 13 · Not started 2. Under construction and past the DLD end date: 3.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Map of the phasesThe map shows 29 of the 29 phases: those with a map pin. Pins mark approximate locations.
Al Jadaf (DM community)
Phases (29)Ordered by registered sales over 24 months
| Project | DLD status | Built | DLD end date / completion | To DLD end date | Units | Sales, 24 mo | Since launch |
|---|---|---|---|---|---|---|---|
| Montage | Under construction | 40% | Aug 2027 9 months to go | 9 months to go | 257 | 245 | +0.9% |
| Binghatti Moonlight | Under construction | 19.2% | Jun 2026 4 months past it | 4 months past it | 286 | 227 | -0.5% |
| Binghatti Twilight | Under construction | 55.4% | Apr 2026 6 months past it | 6 months past it | 277 | 221 | -0.5% |
| Val By Kasco | Under construction | 72.6% | Dec 2026 1 month to go | 1 month to go | 134 | 126 | — |
| Boutique 23 | Under construction | 64.9% | — | — | 328 | 118 | — |
| La Boutique | Under construction | 52.5% | Dec 2026 1 month to go | 1 month to go | 119 | 113 | — |
| Lumiere Heights | Under construction | 2.1% | Jun 2027 7 months to go | 7 months to go | 124 | 103 | — |
| D1 | Completed | 100% | Jun 2015 | — | 523 | 72 | — |
| Volna By Kasco | Completed | 100% | Apr 2026 | — | 71 | 63 | +7.9% |
| Boutique Xll | Completed | 100% | Oct 2023 | — | 129 | 36 | +57.3% |
| Art Bay West | Under construction | 9.1% | — | — | 173 | 34 | — |
| Creek Views | Under construction | 38.8% | — | — | 108 | 33 | +1% |
| Dubai Wharf - Tower 2 | Completed | 100% | Feb 2017 | — | 254 | 33 | — |
| Celeste | Under construction | 3% | Feb 2027 3 months to go | 3 months to go | 49 | 31 | +2.2% |
| Palazzo Versace | Completed | 100% | May 2015 | — | 173 | 29 | — |
| Amazonia | Under construction | 1.4% | Oct 2027 11 months to go | 11 months to go | 76 | 25 | +15.5% |
| Riah Towers | Completed | 100% | Dec 2016 | — | 160 | 24 | — |
| Art Bay East | Under construction | 19.4% | — | — | 103 | 22 | — |
| Dubai Wharf | Completed | 100% | Dec 2016 | — | 124 | 20 | — |
| Iris Amber | Completed | 100% | Sep 2016 | — | 95 | 15 | — |
| Manazel Alkhor | Completed | 100% | Mar 2016 | — | 125 | 9 | — |
| Binghatti Spectre | Not started | 0% | Dec 2028 25 months to go | 25 months to go | 966 | 6 | — |
| The Pearl | Completed | 100% | Dec 2015 | — | 61 | 6 | — |
| Niloofar | Completed | 100% | May 2017 | — | 94 | 2 | — |
| Cascade Ville | Under construction | 22% | Dec 2027 13 months to go | 13 months to go | 0 | 0 | — |
| Babette Sapphire Residence | Under construction | 78.4% | May 2026 5 months past it | 5 months past it | 66 | 0 | — |
| Fala by Kasco | Not started | 0% | Nov 2028 24 months to go | 24 months to go | 116 | 0 | — |
| Nastaran Tower | Completed | 100% | Oct 2011 | — | 181 | 0 | — |
| Dubai Wharf - Tower 1 | Completed | 100% | Mar 2017 | — | 128 | 0 | — |
Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Units not yet completed, by DLD end year
16 phases| DLD end year | Projects | Units |
|---|---|---|
| 2026 | 5 | 882 |
| 2027 | 5 | 506 |
| 2028 | 2 | 1,082 |
| No end date | 4 | 712 |
Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.
More on Jaddaf Waterfront
Own a unit in one of these phases? Track it free
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology