DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 146Completed94 units

Niloofar نيلوفر Al Jadaf · Jaddaf Waterfront by Rmg LimitedAll phases of Jaddaf Waterfront Completed 23 May 2017 (DLD) DLD end date May 2017 DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.

Completed projects cannot be added to My units.

Jaddaf Waterfront skyline across an inlet of Dubai Creek
Area photo: Al Jaddaf, not this project Photo: Timothy A. GonsalvesCC BY-SA 4.0
Completed
May 2017
DLD end date May 2017
Build time
111 months
Feb 2008 → May 2017
Latest sales
—
Fewer than 5 recent sales
1 BR rent
60,000 AED/yr
17 leases, 12 months
Developer
1 project
1 completed · 94 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built

28 October 2026
Built
100%
Latest DLD register reading: 100% built on 28 October 2026 (register readings: 3). Latest DLD inspection: 100% built on 4 October 2017 (inspections: 11).
Every DLD inspection and every change in the register %, newest first
Date % built Source
4 October 2017 100% DLD inspection
17 July 2017 99.2% DLD inspection
17 August 2016 95.7% DLD inspection
28 December 2015 91.3% DLD inspection
29 September 2015 88.8% DLD inspection
18 December 2014 85.5% DLD inspection
9 August 2014 84.1% DLD inspection
31 March 2014 76% DLD inspection
4 November 2013 71% DLD inspection
27 May 2013 59.5% DLD inspection
23 January 2013 55% DLD inspection

Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 5 August 2022, 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗

Site timeline

± 6 months

Our imagery reading holds no milestone for this project yet.

Our reading of historical satellite imagery

Registered period and actual build

Registered period
111 monthsActual build
111 months
Start date
19 February 2008
DLD end date
23 May 2017
Completion date
23 May 2017
Completion vs DLD end date
On the date

Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.

Changes in the DLD register

No change to the end date, status or % built across the register exports we hold.

Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.

DLD registration

DLD services ↗
Developer
DLD project number
146
Escrow agent
Dubai Islamic Bank (Public Joint Stock Company)
Zoning authority
Dubai Development Authority (DDA)
Master project
Jaddaf Waterfront
DLD area
Al Jadaf
Units · villas
94 · 0
Start → DLD end
Feb 2008 → May 2017
Registered unitsStudio 24 · 1 bed 46 · 2 bed 24; sizes 862–1,257 sqft

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: Freehold residential building development located at Culture Village, Al Jadaf. The building is designed to be 4B+G+13 storey levels. The building is designed to be built out of concrete structure and block with internal and external finishes.

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft

No off-plan sales are registered for this project since 2020, so there is no launch price.

Prices are over apartments, the type most sales in this project are.

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Median AED/sqft by quarter

2020-Q1 → 2026-Q2

Median AED/sqft of registered sales per quarter (apartments). Source: DLD. Grey dashed line: DLD area Al Jadaf, median AED/sqft of ready sales of apartments by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

Rents and gross yield

New Ejari rent contracts for apartments in this project, 12 months to 5 November 2026, against the 12 months before. Fewer than 10 ready sales per bedroom count in those 12 months, so no yield is shown.

Bedrooms Median annual rent New contracts Change on a year earlier
Studio AED 45,000 9 -4.3%
1 BR AED 60,000 17 -6%
2 BR AED 83,000 8 -2.4%

New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.

Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.

Mortgage registrations

Home mortgages DLD has registered on units in this project, per quarter, in the 12 quarters to 5 November 2026.

Mortgage registrations on homes per quarter. Source: DLD.

Mortgage registrations in the last 4 quarters (2026-Q1 to 2026-Q4): 1; the amount shows from 5 registrations.

Since the first registration in 2018-Q1: 7 in all.

Counts DLD's mortgage registrations on homes in this project, including pre-registrations on off-plan units and lease-to-own registrations; portfolio and developer mortgages are left out. Amounts are the values DLD registers, shown for 5 registrations or more. A registration says nothing about the lender or the terms.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

The newest 10 of 2 registered sales in the 12 months to 5 November 2026
DateMarketType Size (sqft) Price (AED) AED/sqft
19 June 2026readyApartment · Studio 1,290 900,000 698
17 March 2026readyApartment · Studio 535 650,000 1,215
11 April 2022readyApartment · Studio 535 430,000 804
21 February 2022readyApartment · 1 BR 908 598,220 659
21 February 2022readyApartment · Studio 654 465,330 712
18 October 2021readyApartment · Studio 535 400,000 748
8 October 2021readyApartment · 2 BR 1,280 800,000 625
11 August 2021readyApartment · 1 BR 924 750,000 812
2 August 2021readyApartment · 2 BR 1,289 1,250,000 970
30 June 2021readyApartment · 2 BR 1,257 914,951 728

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

LocationAl Jadaf · Dubai Municipality community

Park · 280 mPark · 340 mPark · 490 mAl Jadaf Metro Station · 560 mBeach · 970 mCarryfood · 990 mDHCC Bldg 24 · 1.1 kmBeach · 1.1 kmCreek Metro Station · 1.2 kminstitute of Medical Aesthetic · 1.2 kmMohammed Bin Rashid Academic Medical Center · 1.2 kmDubai Healthcare City Metro Station · 1.4 kmThe National Charity School · 1.4 kmNew Indian Model School · 1.4 kmProject location© OpenStreetMap contributors · Dubai Municipality · RTA · Makani
Project location Metro and tram Malls and supermarkets Schools and hospitals Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

Metro stationAl Jadaf Metro Station · Green Metro line · 560 m
MallWafi Mall · 1.7 km
SupermarketCarryfood · 990 m
HospitalDHCC Bldg 24 · 1.1 km
SchoolThe National Charity School · 1.4 km
ParkPark · 280 m
BeachBeach · 970 m

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors · RTA

New homes within 1.5 km

Open projects within 1.5 km of the pin: 23, with 5,302 units and villas.

2026: 8822027: 5552028: 1,8772029: 1,276No end date: 712

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Al Jadaf: 31

Open projects in the same DLD area, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Binghatti Cullinan 0% Jun 2027 2,146 524
Binghatti Starlight 63.1% Mar 2026 2,058 481
Montage 40% Aug 2027 1,861 245
Binghatti Moonlight 19.2% Jun 2026 1,983 227
Binghatti Twilight 55.4% Apr 2026 1,834 221
Adeba Azizi 75.5% — — 205
Binghatti Wraith 0% Dec 2027 — 163
Azizi David 2% Sep 2028 2,362 146
Val By Kasco 72.6% Dec 2026 1,695 126
Boutique 23 64.9% — 1,831 118
La Boutique 52.5% Dec 2026 1,634 113
Lumiere Heights 2.1% Jun 2027 — 103

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Al Jadaf

Developer in DLD data Rmg Limited · DLD developer no. 54

Projects registered
1
1 completed · 0 under construction · 0 not started
Units delivered
94
0 in the pipeline

Completed a month or more after their DLD end date: 0 of 1 completed projects with both dates. In 1 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Other projects in Jaddaf Waterfront

DLD lists 28 projects in the master project Jaddaf Waterfront.

Binghatti TwilightUnder construction · 55.4% · Apr 2026
Babette Sapphire ResidenceUnder construction · 78.4% · May 2026
Binghatti MoonlightUnder construction · 19.2% · Jun 2026
Val By KascoUnder construction · 72.6% · Dec 2026
La BoutiqueUnder construction · 52.5% · Dec 2026
CelesteUnder construction · 3% · Feb 2027
Lumiere HeightsUnder construction · 2.1% · Jun 2027
MontageUnder construction · 40% · Aug 2027
AmazoniaUnder construction · 1.4% · Oct 2027
Cascade VilleUnder construction · 22% · Dec 2027
Art Bay WestUnder construction · 9.1% · —
Boutique 23Under construction · 64.9% · —

Questions about Niloofar

When was Niloofar completed?

Niloofar is recorded as completed on 23 May 2017 (DLD register of 1 November 2026).

Who is the developer of Niloofar?

Rmg Limited, as registered with DLD.

What is the DLD project number of Niloofar?

146.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error