DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD master projectAl Satwa

Jumeirah Garden City 40 of 46 phases not yet completed · 4,614 units · 2,571 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026

Jumeirah Garden City has 46 projects in the Dubai Land Department projects register as of 1 November 2026: 40 not yet completed, with 4,614 units and villas. By DLD status: Under construction 29 · Completed 6 · Not started 4 · Pending 7. Under construction and past the DLD end date: 11.

Phases
46
6 completed
Not yet completed
40
29 under construction
Units not yet completed
4,614
units and villas
Sales, 24 mo
2,571
registered with DLD

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Map of the phasesThe map shows 46 of the 46 phases: those with a map pin. Pins mark approximate locations.

Evergrin House · Under construction · Project locationLinea by Holm · Under construction · Project locationHolm One · Under construction · Project locationEvergrin House 2 · Under construction · Project locationKoro One · Completed · Project location171 Garden Heights · Under construction · Project location161 Jumeirah Lane · Under construction · Project locationEnso Jade · Under construction · Project locationCoral by Vision · Completed · Project locationVillea West · Under construction · Project locationRabdan Gardens · Not started / Pending · Project locationOlivia Gardens Residence · Under construction · Project locationThe Grandala · Under construction · Project locationArista One · Completed · Project locationJad 288 · Under construction · Project locationWAHA LIVING by AL YAKKA · Completed · Project locationCavara Central · Under construction · Project locationStamn One · Under construction · Project locationStamn Yuni · Under construction · Project locationDGM Vision · Completed · Project locationMayfair Gardens By Majid · Under construction · Project locationThe Elysian · Under construction · Project locationElmora · Not started / Pending · Project locationVibe · Under construction · Project locationWest 5 Residences · Under construction · Project locationEnso Amber · Under construction · Project locationAlba Tower · Under construction · Project locationChelsea Gardens · Under construction · Project locationJardin Astral · Under construction · Project locationElemental 22 · Under construction · Project locationTrillium Heights · Under construction · Project locationPrestige Gardens by Prestige One · Not started / Pending · Project locationWhitestone Residence · Under construction · Project locationHyde Walk Residence by Imtiaz · Completed · Project locationPurvanchal Triana Residences · Under construction · Project locationBrand Centro · Under construction · Project locationEVERGRIN House 4 · Under construction · Project locationOnaya Residences by Kaya · Under construction · Project locationHolm Central · Not started / Pending · Project locationProject 3168, Al Satwa · Not started / Pending · Project locationizzzi.life Lime · Not started / Pending · Project locationThe Key · Not started / Pending · Project locationAxilla · Not started / Pending · Project locationProject 4380, Al Satwa · Not started / Pending · Project locationVillea East · Not started / Pending · Project locationAD Residences · Not started / Pending · Project locationDubai Municipality · Makani
Under construction Not started / Pending Completed

Al Satwa (DM community)

Phases (46)Ordered by registered sales over 24 months

Phases (46)
ProjectDLD status Built DLD end date / completion To DLD end date Units Sales, 24 mo Since launch
Evergrin HouseUnder construction 54.5% Jun 2026 4 months past it 4 months past it 219 211 +3.9%
Linea by HolmUnder construction 0.7% Jun 2028 19 months to go 19 months to go 210 195 +1.8%
Holm OneUnder construction 17.7% Mar 2028 16 months to go 16 months to go 218 194 +4.1%
Evergrin House 2Under construction 10.3% Dec 2026 1 month to go 1 month to go 193 160 +0.1%
Koro OneCompleted 100% Apr 2026 — 147 145 —
171 Garden HeightsUnder construction 33.7% Dec 2026 1 month to go 1 month to go 159 142 +16.5%
161 Jumeirah LaneUnder construction 70% Mar 2026 8 months past it 8 months past it 161 137 +12.3%
Enso JadeUnder construction 42.1% Jun 2026 4 months past it 4 months past it 105 105 —
Coral by VisionCompleted 100% Feb 2026 — 88 81 +0.9%
Villea WestUnder construction 4.1% Nov 2027 12 months to go 12 months to go 229 80 +1.7%
Rabdan GardensNot started 0% Mar 2028 16 months to go 16 months to go 90 80 +4.8%
Olivia Gardens ResidenceUnder construction 5.5% Apr 2027 5 months to go 5 months to go 78 73 -12.3%
The GrandalaUnder construction 90.7% Jan 2026 9 months past it 9 months past it 86 71 +7.4%
Arista OneCompleted 100% Sep 2025 — 64 69 -8.5%
Jad 288Under construction 1.9% Dec 2027 13 months to go 13 months to go 222 62 +0.5%
WAHA LIVING by AL YAKKACompleted 100% Apr 2026 — 71 58 +0.4%
Cavara CentralUnder construction 43.1% Jul 2026 3 months past it 3 months past it 166 57 +5.5%
Stamn OneUnder construction 42.1% Oct 2026 This month This month 77 52 -4.5%
Stamn YuniUnder construction 11.6% Mar 2027 4 months to go 4 months to go 88 52 +0.5%
DGM VisionCompleted 100% May 2026 — 95 52 +7.2%
Mayfair Gardens By MajidUnder construction 70.1% Aug 2026 2 months past it 2 months past it 64 49 -6.8%
The ElysianUnder construction 4.5% Aug 2027 9 months to go 9 months to go 84 49 -16%
ElmoraNot started 0% Feb 2028 15 months to go 15 months to go 85 48 -1.5%
VibeUnder construction 1.5% Aug 2028 21 months to go 21 months to go 212 47 +5.7%
West 5 ResidencesUnder construction 8.2% Apr 2027 5 months to go 5 months to go 130 44 -1%
Enso AmberUnder construction 11.3% Jun 2026 4 months past it 4 months past it 71 43 -5.7%
Alba TowerUnder construction 30.9% Jun 2028 19 months to go 19 months to go 73 40 +7.7%
Chelsea GardensUnder construction 10.3% Feb 2027 3 months to go 3 months to go 59 35 -5.5%
Jardin AstralUnder construction 45.1% Aug 2026 3 months past it 3 months past it 44 34 —
Elemental 22Under construction 25.9% May 2028 18 months to go 18 months to go 42 22 —
Trillium HeightsUnder construction 61.6% Dec 2025 10 months past it 10 months past it 56 18 —
Prestige Gardens by Prestige OneNot started 0% Sep 2028 22 months to go 22 months to go 48 17 —
Whitestone ResidenceUnder construction 3% Oct 2026 This month This month 47 14 —
Hyde Walk Residence by ImtiazCompleted 100% Nov 2025 — 89 13 —
Purvanchal Triana ResidencesUnder construction 26.4% Mar 2027 4 months to go 4 months to go 72 11 —
Brand CentroUnder construction 90% Jul 2026 3 months past it 3 months past it 56 10 —
EVERGRIN House 4Under construction 23.6% Jan 2027 2 months to go 2 months to go 89 1 —
Onaya Residences by KayaUnder construction 37.7% Jun 2026 4 months past it 4 months past it 41 0 —
Holm CentralNot started 0% Jun 2028 19 months to go 19 months to go 461 0 —
Project 3168, Al SatwaPending 0% Dec 2027 13 months to go 13 months to go 0 0 —
izzzi.life LimePending 3% Jun 2029 31 months to go 31 months to go 218 0 —
The KeyPending 0% Jan 2029 26 months to go 26 months to go 54 0 —
AxillaPending 0% Mar 2028 16 months to go 16 months to go 54 0 —
Project 4380, Al SatwaPending 0% Sep 2028 22 months to go 22 months to go 0 0 —
Villea EastPending 0% Sep 2028 22 months to go 22 months to go 113 0 —
AD ResidencesPending 6.4% Apr 2028 17 months to go 17 months to go 140 0 —

Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Units not yet completed, by DLD end year

40 phases
2025: 562026: 1,4892027: 1,0512028: 1,7462029: 272

Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.

More on Jumeirah Garden City

Own a unit in one of these phases? Track it free

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology