DLD master projectAl Satwa
Jumeirah Garden City 40 of 46 phases not yet completed · 4,614 units · 2,571 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026
Jumeirah Garden City has 46 projects in the Dubai Land Department projects register as of 1 November 2026: 40 not yet completed, with 4,614 units and villas. By DLD status: Under construction 29 · Completed 6 · Not started 4 · Pending 7. Under construction and past the DLD end date: 11.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Map of the phasesThe map shows 46 of the 46 phases: those with a map pin. Pins mark approximate locations.
Al Satwa (DM community)
Phases (46)Ordered by registered sales over 24 months
| Project | DLD status | Built | DLD end date / completion | To DLD end date | Units | Sales, 24 mo | Since launch |
|---|---|---|---|---|---|---|---|
| Evergrin House | Under construction | 54.5% | Jun 2026 4 months past it | 4 months past it | 219 | 211 | +3.9% |
| Linea by Holm | Under construction | 0.7% | Jun 2028 19 months to go | 19 months to go | 210 | 195 | +1.8% |
| Holm One | Under construction | 17.7% | Mar 2028 16 months to go | 16 months to go | 218 | 194 | +4.1% |
| Evergrin House 2 | Under construction | 10.3% | Dec 2026 1 month to go | 1 month to go | 193 | 160 | +0.1% |
| Koro One | Completed | 100% | Apr 2026 | — | 147 | 145 | — |
| 171 Garden Heights | Under construction | 33.7% | Dec 2026 1 month to go | 1 month to go | 159 | 142 | +16.5% |
| 161 Jumeirah Lane | Under construction | 70% | Mar 2026 8 months past it | 8 months past it | 161 | 137 | +12.3% |
| Enso Jade | Under construction | 42.1% | Jun 2026 4 months past it | 4 months past it | 105 | 105 | — |
| Coral by Vision | Completed | 100% | Feb 2026 | — | 88 | 81 | +0.9% |
| Villea West | Under construction | 4.1% | Nov 2027 12 months to go | 12 months to go | 229 | 80 | +1.7% |
| Rabdan Gardens | Not started | 0% | Mar 2028 16 months to go | 16 months to go | 90 | 80 | +4.8% |
| Olivia Gardens Residence | Under construction | 5.5% | Apr 2027 5 months to go | 5 months to go | 78 | 73 | -12.3% |
| The Grandala | Under construction | 90.7% | Jan 2026 9 months past it | 9 months past it | 86 | 71 | +7.4% |
| Arista One | Completed | 100% | Sep 2025 | — | 64 | 69 | -8.5% |
| Jad 288 | Under construction | 1.9% | Dec 2027 13 months to go | 13 months to go | 222 | 62 | +0.5% |
| WAHA LIVING by AL YAKKA | Completed | 100% | Apr 2026 | — | 71 | 58 | +0.4% |
| Cavara Central | Under construction | 43.1% | Jul 2026 3 months past it | 3 months past it | 166 | 57 | +5.5% |
| Stamn One | Under construction | 42.1% | Oct 2026 This month | This month | 77 | 52 | -4.5% |
| Stamn Yuni | Under construction | 11.6% | Mar 2027 4 months to go | 4 months to go | 88 | 52 | +0.5% |
| DGM Vision | Completed | 100% | May 2026 | — | 95 | 52 | +7.2% |
| Mayfair Gardens By Majid | Under construction | 70.1% | Aug 2026 2 months past it | 2 months past it | 64 | 49 | -6.8% |
| The Elysian | Under construction | 4.5% | Aug 2027 9 months to go | 9 months to go | 84 | 49 | -16% |
| Elmora | Not started | 0% | Feb 2028 15 months to go | 15 months to go | 85 | 48 | -1.5% |
| Vibe | Under construction | 1.5% | Aug 2028 21 months to go | 21 months to go | 212 | 47 | +5.7% |
| West 5 Residences | Under construction | 8.2% | Apr 2027 5 months to go | 5 months to go | 130 | 44 | -1% |
| Enso Amber | Under construction | 11.3% | Jun 2026 4 months past it | 4 months past it | 71 | 43 | -5.7% |
| Alba Tower | Under construction | 30.9% | Jun 2028 19 months to go | 19 months to go | 73 | 40 | +7.7% |
| Chelsea Gardens | Under construction | 10.3% | Feb 2027 3 months to go | 3 months to go | 59 | 35 | -5.5% |
| Jardin Astral | Under construction | 45.1% | Aug 2026 3 months past it | 3 months past it | 44 | 34 | — |
| Elemental 22 | Under construction | 25.9% | May 2028 18 months to go | 18 months to go | 42 | 22 | — |
| Trillium Heights | Under construction | 61.6% | Dec 2025 10 months past it | 10 months past it | 56 | 18 | — |
| Prestige Gardens by Prestige One | Not started | 0% | Sep 2028 22 months to go | 22 months to go | 48 | 17 | — |
| Whitestone Residence | Under construction | 3% | Oct 2026 This month | This month | 47 | 14 | — |
| Hyde Walk Residence by Imtiaz | Completed | 100% | Nov 2025 | — | 89 | 13 | — |
| Purvanchal Triana Residences | Under construction | 26.4% | Mar 2027 4 months to go | 4 months to go | 72 | 11 | — |
| Brand Centro | Under construction | 90% | Jul 2026 3 months past it | 3 months past it | 56 | 10 | — |
| EVERGRIN House 4 | Under construction | 23.6% | Jan 2027 2 months to go | 2 months to go | 89 | 1 | — |
| Onaya Residences by Kaya | Under construction | 37.7% | Jun 2026 4 months past it | 4 months past it | 41 | 0 | — |
| Holm Central | Not started | 0% | Jun 2028 19 months to go | 19 months to go | 461 | 0 | — |
| Project 3168, Al Satwa | Pending | 0% | Dec 2027 13 months to go | 13 months to go | 0 | 0 | — |
| izzzi.life Lime | Pending | 3% | Jun 2029 31 months to go | 31 months to go | 218 | 0 | — |
| The Key | Pending | 0% | Jan 2029 26 months to go | 26 months to go | 54 | 0 | — |
| Axilla | Pending | 0% | Mar 2028 16 months to go | 16 months to go | 54 | 0 | — |
| Project 4380, Al Satwa | Pending | 0% | Sep 2028 22 months to go | 22 months to go | 0 | 0 | — |
| Villea East | Pending | 0% | Sep 2028 22 months to go | 22 months to go | 113 | 0 | — |
| AD Residences | Pending | 6.4% | Apr 2028 17 months to go | 17 months to go | 140 | 0 | — |
Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Units not yet completed, by DLD end year
40 phases| DLD end year | Projects | Units |
|---|---|---|
| 2025 | 1 | 56 |
| 2026 | 14 | 1,489 |
| 2027 | 10 | 1,051 |
| 2028 | 13 | 1,746 |
| 2029 | 2 | 272 |
Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.
More on Jumeirah Garden City
Own a unit in one of these phases? Track it free
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology