DLD master projectAl Hebiah First
Motor City 16 of 22 phases not yet completed · 12,759 units · 7,428 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026
Motor City has 22 projects in the Dubai Land Department projects register as of 1 November 2026: 16 not yet completed, with 12,759 units and villas. By DLD status: Under construction 11 · Not started 3 · Completed 6 · Pending 2. Under construction and past the DLD end date: 2.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Map of the phasesThe map shows 21 of the 22 phases: those with a map pin. Pins mark approximate locations.
Al Hebiah First (DM community)
Phases (22)Ordered by registered sales over 24 months
| Project | DLD status | Built | DLD end date / completion | To DLD end date | Units | Sales, 24 mo | Since launch |
|---|---|---|---|---|---|---|---|
| Sobha Solis | Under construction | 17.9% | Dec 2028 25 months to go | 25 months to go | 2,351 | 2,143 | +3.2% |
| Sobha Orbis | Under construction | 18.2% | Dec 2028 25 months to go | 25 months to go | 3,002 | 1,895 | +3% |
| Binghatti Skyterraces | Not started | 0% | Oct 2027 11 months to go | 11 months to go | 1,886 | 887 | -9.8% |
| Sierra By Iman | Under construction | 3.7% | Jun 2029 31 months to go | 31 months to go | 598 | 544 | +0.1% |
| Takaya | Under construction | 15.6% | Dec 2027 13 months to go | 13 months to go | 822 | 484 | +19.7% |
| 15 Cascade | Under construction | 5.5% | Sep 2028 22 months to go | 22 months to go | 442 | 409 | +0.2% |
| Ananda Residences | Under construction | 3.2% | May 2028 18 months to go | 18 months to go | 1,027 | 278 | +25.1% |
| Casa Flores And Eden Apartments | Completed | 100% | Jun 2019 | — | 273 | 182 | — |
| Beverly Grande | Not started | 0.5% | Dec 2027 13 months to go | 13 months to go | 296 | 148 | +11.5% |
| Mirdad | Under construction | 6% | Dec 2028 25 months to go | 25 months to go | 1,114 | 142 | +0.8% |
| OIA Residence | Completed | 100% | Jul 2018 | — | 269 | 112 | — |
| Velos Residence | Under construction | 6.6% | Oct 2028 23 months to go | 23 months to go | 413 | 107 | -3% |
| The Community Motor City | Under construction | 95.1% | Oct 2025 12 months past it | 12 months past it | 433 | 82 | +26.4% |
| Green Community Motor City, Phase Ii - Casa Familia | Completed | 100% | Nov 2017 | — | 95 | 15 | — |
| Capital One | Under construction | 20% | Feb 2027 3 months to go | 3 months to go | 257 | 0 | — |
| Monarch | Under construction | 32.3% | Oct 2026 1 month past it | 1 month past it | 47 | 0 | — |
| O1NE District - Dawn | Not started | 0% | Jan 2030 38 months to go | 38 months to go | 71 | 0 | — |
| Project 2319, Al Hebiah First | Pending | 0% | — | — | 0 | 0 | — |
| Project 4427, Al Hebiah First | Pending | 0% | Jun 2029 31 months to go | 31 months to go | 0 | 0 | — |
| Apex Atrium | Completed | 100% | Jul 2010 | — | 73 | 0 | — |
| Daytona House | Completed | 100% | Oct 2009 | — | 37 | 0 | — |
| Detroit House | Completed | 100% | Jul 2010 | — | 159 | 0 | — |
Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Units not yet completed, by DLD end year
16 phases| DLD end year | Projects | Units |
|---|---|---|
| 2025 | 1 | 433 |
| 2026 | 1 | 47 |
| 2027 | 4 | 3,261 |
| 2028 | 6 | 8,349 |
| 2029 | 2 | 598 |
| 2030 | 1 | 71 |
| No end date | 1 | 0 |
Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.
More on Motor City
Own a unit in one of these phases? Track it free
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology