DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD master projectNadd Hessa

Silicon Oasis 13 of 74 phases not yet completed · 4,432 units · 5,231 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026

Silicon Oasis has 74 projects in the Dubai Land Department projects register as of 1 November 2026: 13 not yet completed, with 4,432 units and villas. By DLD status: Under construction 11 · Completed 61 · Not started 1 · Pending 1. Under construction and past the DLD end date: 3.

Phases
74
61 completed
Not yet completed
13
11 under construction
Units not yet completed
4,432
units and villas
Sales, 24 mo
5,231
registered with DLD

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Map of the phasesThe map shows 73 of the 74 phases: those with a map pin. Pins mark approximate locations.

Timez By Danube · Under construction · Approximate project locationOasiz 2 by Danube · Under construction · Project locationThe Hillgate · Under construction · Project locationOasiz 1 by Danube · Under construction · Project locationSerenova · Under construction · Approximate project locationSilicon Gate 1 · Completed · Project locationTria By Deyaar · Under construction · Project locationOasis Loft · Under construction · Project locationAltia One · Completed · Project locationSelicon Star 2 · Completed · Project locationArabian Gate · Completed · Project locationBelle Vie By Zimaya · Under construction · Project locationPalace Tower · Completed · Project locationAura Elite · Under construction · Project locationBinghatti Stars · Completed · Project locationAura Prestige · Under construction · Project locationBinghatti Apartments · Completed · Project locationAura Elegance · Completed · Project locationImperial · Completed · Project locationSilicon Heights · Completed · Project locationSilicon Gates 4 · Completed · Project locationPearls by Vision · Completed · Project locationAxis Residences 1 · Completed · Project locationTopaz Residences 3 · Completed · Project locationUniestate Millennium Tower · Completed · Project locationAltia Residence · Completed · Project locationSOLEN RESIDENCE by Jamal Living · Under construction · Project locationSilicon HEIGHTS2 · Completed · Project locationAxis Residences 4 · Completed · Project locationLa Vista 03 · Completed · Project locationThe Dunes · Completed · Project locationLa Visita 01 · Completed · Project locationLynx · Completed · Project locationTopaz Residences 2 · Completed · Project locationBinghatti Views · Completed · Project locationMas Tower · Completed · Project locationAxis Residences 2 · Completed · Project locationAxis Residences 6 · Completed · Project locationJade Residence · Completed · Project locationCoral Residence · Completed · Project locationAxis Residences 8 · Completed · Project locationAxis Silver · Completed · Project locationSilicon Gate 3 · Completed · Project locationPlatinum Residence 1 · Completed · Project locationRuby Residence · Completed · Approximate project locationLa Visita 02 · Completed · Project locationSilicon Boulevard · Completed · Project locationCordoba Palace · Completed · Project locationSapphire Residence · Completed · Project locationLe Presidium · Completed · Project locationTopaz Residences 1 · Completed · Project locationOasis High Park · Completed · Project locationAxis Residences 3 · Completed · Project locationBinghatti Point · Completed · Project locationSevanam Crown · Completed · Project locationPlatinum Residence 2 · Completed · Project locationSilicon GATE2 · Completed · Project locationAxis Residences 5 · Completed · Project locationAl Falak Residence · Completed · Project locationS.P Oasis · Completed · Project locationOasis Star · Completed · Project locationSunshine Residence · Completed · Project locationSilicon Avenue · Completed · Project locationYigo Luxe · Not started / Pending · Project locationElyra Residences by Enaam · Not started / Pending · Project locationLa Vista 04 · Completed · Project locationLa Vista 05 · Completed · Project locationLa Vista 06 · Completed · Project locationIt Plaza · Completed · Project locationCambridge Business Centre · Completed · Project locationThe Apricot · Completed · Project locationPalacio · Completed · Project locationSilicon Information Technology Tower · Completed · Project location© OpenStreetMap contributors · Dubai Municipality · Makani
Under construction Not started / Pending Completed Approximate project locations

Nadd Hessa (DM community)

Phases (74)Ordered by registered sales over 24 months

Phases (74)
ProjectDLD status Built DLD end date / completion To DLD end date Units Sales, 24 mo Since launch
Timez By DanubeUnder construction 21.5% Jul 2028 20 months to go 20 months to go 1,191 1,143 -1.6%
Oasiz 2 by DanubeUnder construction 31% Nov 2027 12 months to go 12 months to go 483 474 +4%
The HillgateUnder construction 3.1% Jun 2028 19 months to go 19 months to go 356 333 +1.2%
Oasiz 1 by DanubeUnder construction 30.4% Nov 2027 12 months to go 12 months to go 410 269 +1.7%
SerenovaUnder construction 1.6% Mar 2028 16 months to go 16 months to go 222 223 —
Silicon Gate 1Completed 100% Jan 2014 — 888 194 —
Tria By DeyaarUnder construction 94.1% Jun 2025 16 months past it 16 months past it 717 186 +24.4%
Oasis LoftUnder construction 50.1% Sep 2026 1 month past it 1 month past it 164 168 —
Altia OneCompleted 100% Oct 2025 — 123 140 +6.5%
Selicon Star 2Completed 100% Dec 2012 — 119 125 —
Arabian GateCompleted 100% Oct 2020 — 716 113 —
Belle Vie By ZimayaUnder construction 11% Mar 2028 16 months to go 16 months to go 116 109 +4.6%
Palace TowerCompleted 100% Aug 2009 — 597 81 —
Aura EliteUnder construction 44.3% Apr 2026 6 months past it 6 months past it 86 69 -1.3%
Binghatti StarsCompleted 100% Oct 2019 — 362 69 —
Aura PrestigeUnder construction 40.1% Nov 2026 This month This month 81 67 +6.3%
Binghatti ApartmentsCompleted 100% Dec 2015 — 224 66 —
Aura EleganceCompleted 100% Feb 2026 — 109 64 +29.1%
ImperialCompleted 100% May 2010 — 126 61 —
Silicon HeightsCompleted 100% Aug 2011 — 279 60 —
Silicon Gates 4Completed 100% Dec 2015 — 316 56 —
Pearls by VisionCompleted 100% Aug 2025 — 114 56 +24.4%
Axis Residences 1Completed 100% Sep 2009 — 316 52 —
Topaz Residences 3Completed 100% Jan 2020 — 112 48 —
Uniestate Millennium TowerCompleted 100% Mar 2012 — 128 46 —
Altia ResidenceCompleted 100% Oct 2016 — 101 46 —
SOLEN RESIDENCE by Jamal LivingUnder construction 21.7% Oct 2027 11 months to go 11 months to go 87 43 —
Silicon HEIGHTS2Completed 100% Jun 2015 — 250 43 —
Axis Residences 4Completed 100% Oct 2009 — 128 42 —
La Vista 03Completed 100% Apr 2015 — 128 39 —
The DunesCompleted 100% Mar 2009 — 189 38 —
La Visita 01Completed 100% Mar 2014 — 128 37 —
LynxCompleted 100% May 2018 — 237 37 —
Topaz Residences 2Completed 100% Jan 2022 — 202 36 —
Binghatti ViewsCompleted 100% Apr 2017 — 174 33 —
Mas TowerCompleted 100% Dec 2023 — 96 33 —
Axis Residences 2Completed 100% Feb 2014 — 284 32 —
Axis Residences 6Completed 100% Sep 2013 — 112 32 —
Jade ResidenceCompleted 100% Oct 2009 — 97 30 —
Coral ResidenceCompleted 100% Feb 2010 — 145 29 —
Axis Residences 8Completed 100% May 2010 — 112 29 —
Axis SilverCompleted 100% Jun 2015 — 120 28 —
Silicon Gate 3Completed 100% Feb 2009 — 124 27 —
Platinum Residence 1Completed 100% May 2015 — 120 26 —
Ruby ResidenceCompleted 100% Feb 2010 — 138 24 —
La Visita 02Completed 100% Jun 2013 — 128 22 —
Silicon BoulevardCompleted 100% May 2010 — 206 22 —
Cordoba PalaceCompleted 100% Apr 2012 — 136 22 —
Sapphire ResidenceCompleted 100% Feb 2010 — 90 21 —
Le PresidiumCompleted 100% Aug 2016 — 200 21 —
Topaz Residences 1Completed 100% Jun 2016 — 136 21 —
Oasis High ParkCompleted 100% Jul 2009 — 159 19 —
Axis Residences 3Completed 100% May 2009 — 128 19 —
Binghatti PointCompleted 100% Feb 2022 — 127 18 +96.6%
Sevanam CrownCompleted 100% Nov 2009 — 126 16 —
Platinum Residence 2Completed 100% May 2015 — 80 14 —
Silicon GATE2Completed 100% May 2014 — 132 13 —
Axis Residences 5Completed 100% May 2010 — 112 13 —
Al Falak ResidenceCompleted 100% Dec 2015 — 97 12 —
S.P OasisCompleted 100% Apr 2010 — 68 10 —

Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Units not yet completed, by DLD end year

13 phases
2025: 7172026: 3312027: 9802028: 1,8852029: 1552030: 364

Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.

More on Silicon Oasis

Own a unit in one of these phases? Track it free

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology