DLD project no. 3712Under construction151 units
AL WALEED w.s 1 الوليد دبليو.اس 1 18.3% built (DLD register as of 1 November 2026) · DLD end date Feb 2027 · 3 months to go DLD register as of 1 November 2026. The end date is the one registered with DLD, not a handover forecast.
CompletionDLD readings of % built, beside the share of the planned period gone
% built and period elapsed
1 November 2026Two separate measures: one is DLD's % built, the other is time on the calendar.
| Date | % built | Source |
|---|---|---|
| 18 June 2026 | 18.3% | DLD inspection |
| 1 May 2025 | 0% | DLD inspection |
Source: Dubai Land Department projects register, as of 1 November 2026. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗ Period elapsed: our calculation from DLD’s start and end dates.
Our completion calculation
Pace since the last two DLD readings: —
Our calculation from DLD readings. It describes the recent pace only; it is not a forecast of the completion date.
Site timeline
± 6 monthsEach date is ± 6 months. This is our reading, not DLD's; no image is shown. Read from imagery dated 28 April 2023 to 18 February 2026; method imagery-v1.
Changes in the DLD register
Source: DLD projects register exports, compared by CraneScore. Dates and progress are those in the Dubai Land Department projects register on each register date, not inspection dates. DLD can revise the end date; we keep every register reading from 28 October 2026 on and list the changes here.
Inspection photos and reports
DLD’s Project Status service (Mashrooi) shows inspection details and site photos. Look the project up by its number.
CraneScore links to DLD and does not copy or host its photos or reports.
DLD registration
DLD services ↗Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.
Description in the DLD register: Our new project Al Waleed w.s 1 is located in Wadi Al Safa 5, under the Dubai Land Residences LLC as main Developer and Al Waleed Deveopment LLC as sub Developer. Our building consists of B+G+2P+12 Floors + Roof with total built up area 250,624.01 Sq.ft and GFA 130,056.64 Sq.ft Total number of flats 151 which are in detail Studio: 22 no?s; 1 BR: 83 no?s; 2 BR: 46 no?s. Building has total 155 parking and swimming pool and gym facility. The building combines elegant, modern design with high-quality finishes, while providing comfort for residents.
DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae
Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.
AED · sqft
Fewer than 5 sales with a size were registered in the first 90 days, so no launch price is shown.
Prices are over apartments, the type most sales in this project are.
Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.
Registered sales per quarter
| Quarter | Registered sales |
|---|---|
| 2026-Q1 | 1 (off-plan 1, ready 0) |
| 2026-Q3 | 1 (off-plan 1, ready 0) |
Registered sales per quarter, off-plan and ready units. Source: DLD.
Rents in DLD area Wadi Al Safa 5
New Ejari rent contracts for apartments across DLD area Wadi Al Safa 5, 12 months to 5 November 2026, against the 12 months before: the rent level around this project. No yield is shown before the project is completed.
| Bedrooms | Median annual rent | New contracts | Change on a year earlier |
|---|---|---|---|
| Studio | AED 40,000 | 918 | +2.6% |
| 1 BR | AED 55,000 | 1,194 | 0% |
| 2 BR | AED 73,000 | 653 | +4.3% |
| 3 BR | AED 100,000 | 63 | -8.6% |
New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.
Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.
Registered sales
The newest sales DLD has registered in this project, as DLD publishes them.
| Date | Market | Type | Size (sqft) | Price (AED) | AED/sqft |
|---|---|---|---|---|---|
| 14 July 2026 | off-plan | Apartment · 2 BR | 1,277 | 1,417,762 | 1,110 |
| 6 February 2026 | off-plan | Apartment · Studio | 421 | 630,981 | 1,499 |
Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.
Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence
Looking for a unit in this or similar projects?
Tell us what you are looking for in AL WALEED w.s 1 or similar projects. We reply by e-mail, and your request stays with CraneScore.
Estimated value range
Not enough registered off-plan sales for an estimate (at least 5 of one bedroom count in 12 months).
Automated estimate from registered off-plan sales (developer sales and resales mixed); not a valuation by a registered valuer; not for mortgage or court use.
Payment scenarioEnter the developer’s plan to see what you pay and when. Handover starts at the DLD end date (Feb 2027); move it with the slider.
A scenario from your own inputs, not this project's verified payment plan.
Common plans
Plan shares add up to 100% (must be 100%).
Payments per quarter
AED| Quarter | Paid |
|---|---|
| 2026-Q4 | AED 445,000 · AED 445,000 paid so far |
| 2027-Q1 | AED 600,000 · AED 1,045,000 paid so far |
Payments per quarter, AED, fees included. Illustration from your inputs.
The DLD fee (4% of the price) and the fees above are paid at booking. With a resale price, the unit is sold at handover and the buyer takes over any unpaid balance; agent fees, mortgage costs and service charges are left out. An illustration from your inputs, not financial advice.
Mortgage for a unit here
Questions about financing a unit in AL WALEED w.s 1? Leave your details and we reply by e-mail. Your request stays with CraneScore.
LocationWadi Al Safa 5 · Dubai Municipality community
Places near the project
Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.
School ratings: KHDA’s school directory ↗ · Report a wrong location
Dubai Municipality · Makani · © OpenStreetMap contributors
New homes within 1.5 km
Open projects within 1.5 km of the pin: 73, with 17,845 units and villas.
| DLD end year | Projects | Units and villas |
|---|---|---|
| 2026 | 10 | 1,889 |
| 2027 | 31 | 5,703 |
| 2028 | 22 | 5,910 |
| 2029 | 6 | 3,144 |
| 2030 | 1 | 565 |
| No end date | 3 | 634 |
Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.
Open projects in Wadi Al Safa 5: 108
Open projects in the same DLD area with a DLD end year from 2026 to 2028, by registered sales in 24 months.
| Project | Built | DLD end date | AED/sqft, 12 mo | Sales, 24 mo |
|---|---|---|---|---|
| Peace Lagoons by Peace Homes | 4.2% | Sep 2028 | 1,410 | 795 |
| Verdes by Haven 1 | 17.7% | May 2028 | 1,374 | 658 |
| Cove Grand Residence by Imtiaz | 13.4% | Dec 2027 | 1,531 | 526 |
| Samana Boulevard Heights | 2.5% | Dec 2028 | 1,522 | 526 |
| La Tilia at Villanova Phase 2 | 10.6% | Aug 2028 | 1,487 | 477 |
| La Tilia at Villanova Phase 1 | 13.8% | Aug 2028 | 1,435 | 456 |
| Samana IBIZA | 5.5% | Feb 2028 | 1,426 | 444 |
| Samana Parkville | 13.9% | Sep 2028 | 1,503 | 419 |
| Athlon By Al Dar 1 | 27.3% | May 2028 | 1,574 | 387 |
| The Boulevard By Prestige One | 10.6% | Nov 2027 | 1,359 | 375 |
| Kensington Gardens | 0% | Sep 2027 | 1,354 | 336 |
| Terra Tower | 7.4% | Apr 2027 | 1,550 | 323 |
AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.
Developer in DLD data Al Waleed Development L.L.C · DLD developer no. 1532
Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.
Other projects in Dubai Land Residence Complex
DLD lists 118 projects in the master project Dubai Land Residence Complex.
Questions about AL WALEED w.s 1
When is AL WALEED w.s 1's handover?
DLD lists an end date of Feb 2027 (register of 1 November 2026); the SPA sets the handover terms.
Is AL WALEED w.s 1 past its DLD end date?
No. Its DLD end date is Feb 2027, 3 months after the register of 1 November 2026.
How far along is AL WALEED w.s 1?
18.3% built in the DLD register of 1 November 2026.
Who is the developer of AL WALEED w.s 1?
Al Waleed Development L.L.C, as registered with DLD.
What is the DLD project number of AL WALEED w.s 1?
3712.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error