DLD master projectWadi Al Safa 5
Dubai Land Residence Complex 95 of 119 phases not yet completed · 24,264 units · 13,646 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026
Dubai Land Residence Complex has 119 projects in the Dubai Land Department projects register as of 1 November 2026: 95 not yet completed, with 24,264 units and villas. By DLD status: Under construction 63 · Completed 24 · Not started 20 · Pending 12. Under construction and past the DLD end date: 5.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Map of the phasesThe map shows 119 of the 119 phases: those with a map pin. Pins mark approximate locations.
Wadi Al Safa 5 (DM community)
Phases (119)Ordered by registered sales over 24 months
| Project | DLD status | Built | DLD end date / completion | To DLD end date | Units | Sales, 24 mo | Since launch |
|---|---|---|---|---|---|---|---|
| Peace Lagoons by Peace Homes | Under construction | 4.2% | Sep 2028 22 months to go | 22 months to go | 1,000 | 795 | +6.6% |
| Sky Courts | Completed | 100% | Feb 2011 | — | 2,859 | 675 | — |
| Peace Lagoons II by Peace Homes | Under construction | 4% | Jan 2029 26 months to go | 26 months to go | 831 | 553 | +2.1% |
| Samana Boulevard Heights | Under construction | 2.5% | Dec 2028 25 months to go | 25 months to go | 541 | 526 | -4% |
| Cove Grand Residence by Imtiaz | Under construction | 13.4% | Dec 2027 13 months to go | 13 months to go | 538 | 526 | +4.2% |
| Samana IBIZA | Under construction | 5.5% | Feb 2028 15 months to go | 15 months to go | 455 | 444 | +2.9% |
| Samana Parkville | Under construction | 13.9% | Sep 2028 22 months to go | 22 months to go | 428 | 419 | -2.4% |
| The Boulevard By Prestige One | Under construction | 10.6% | Nov 2027 12 months to go | 12 months to go | 387 | 375 | -0.7% |
| Kensington Gardens | Not started | 0% | Sep 2027 10 months to go | 10 months to go | 361 | 336 | +0.1% |
| Terra Tower | Under construction | 7.4% | Apr 2027 5 months to go | 5 months to go | 366 | 323 | +9.5% |
| Le Blanc Residence by Imtiaz | Under construction | 6% | Oct 2028 23 months to go | 23 months to go | 323 | 296 | +0.8% |
| Reef 998 | Under construction | 2.1% | Jun 2028 19 months to go | 19 months to go | 339 | 281 | +4.6% |
| Samana IVY Gardens 2 | Under construction | 20% | Dec 2027 13 months to go | 13 months to go | 843 | 271 | -0.6% |
| Cove Edition Residence 2 By Imtiaz | Under construction | 60.1% | Oct 2026 This month | This month | 260 | 270 | +1.8% |
| Cove Edition Residence 4 By Imtiaz | Under construction | 30.2% | Jan 2027 2 months to go | 2 months to go | 260 | 268 | -1.5% |
| Cove Edition Residence 3 By Imtiaz | Under construction | 44% | Dec 2026 1 month to go | 1 month to go | 260 | 267 | -0.1% |
| Cove Edition Residence 6 By Imtiaz | Under construction | 25.9% | Sep 2027 10 months to go | 10 months to go | 264 | 263 | +2.3% |
| Ag Aum Residence | Under construction | 2.4% | Nov 2028 24 months to go | 24 months to go | 260 | 257 | -22.2% |
| Weybridge Gardens 2 | Under construction | 33.7% | — | — | 288 | 249 | +4.2% |
| Cove Boulevard By Imtiaz | Under construction | 10.5% | Oct 2028 23 months to go | 23 months to go | 436 | 243 | +3.9% |
| Floarea Oasis | Under construction | 12.6% | Dec 2028 25 months to go | 25 months to go | 257 | 228 | — |
| Cybele By Wadan | Under construction | 2% | Dec 2027 13 months to go | 13 months to go | 232 | 228 | -2.3% |
| Time 3 | Under construction | 47.1% | Aug 2027 9 months to go | 9 months to go | 288 | 212 | +15.2% |
| Weybridge Gardens 3 | Under construction | 23.9% | Aug 2026 2 months past it | 2 months past it | 208 | 212 | — |
| Samana Park Meadows | Under construction | 38% | Aug 2027 9 months to go | 9 months to go | 221 | 202 | — |
| COVE EDITION RESIDENCE 5 by Imtiaz | Under construction | 26.3% | May 2027 6 months to go | 6 months to go | 198 | 199 | -1.2% |
| Seraph by Wadan | Under construction | 20.9% | Dec 2027 13 months to go | 13 months to go | 190 | 190 | -2.9% |
| Ag Ark Tower | Under construction | 3.2% | Nov 2028 24 months to go | 24 months to go | 189 | 182 | -7.2% |
| Nuve By Zoya | Under construction | 0.8% | Jun 2028 19 months to go | 19 months to go | 234 | 177 | -8.7% |
| Verdania 1 | Under construction | 16.7% | Mar 2027 4 months to go | 4 months to go | 208 | 173 | -20.3% |
| Milos By Karma | Not started | 0.4% | Apr 2027 5 months to go | 5 months to go | 195 | 170 | +0.2% |
| Celesto Tower | Under construction | 3.9% | Dec 2027 13 months to go | 13 months to go | 271 | 156 | -0.5% |
| Sky Line By Peace Homes | Not started | 0% | May 2030 42 months to go | 42 months to go | 565 | 147 | -4.5% |
| Weybridge Gardens 5 | Not started | 0% | Sep 2027 10 months to go | 10 months to go | 168 | 135 | +1.5% |
| Empire Gardens | Not started | 0% | Dec 2028 25 months to go | 25 months to go | 221 | 130 | +6.5% |
| ARLINGTON PARK By MAJID | Under construction | 5.7% | Dec 2027 13 months to go | 13 months to go | 140 | 128 | +2% |
| AUM 99 Residences | Not started | 0% | Mar 2029 28 months to go | 28 months to go | 186 | 123 | -0.5% |
| Bliss Tower | Under construction | 92.5% | Dec 2026 1 month to go | 1 month to go | 131 | 116 | +16.3% |
| Weston | Not started | 0% | Dec 2028 25 months to go | 25 months to go | 373 | 115 | — |
| Bliss Homes | Completed | 100% | Dec 2024 | — | 105 | 112 | -9.4% |
| Blue Wave | Completed | 100% | Jan 2023 | — | 578 | 103 | — |
| Reef 1000 | Under construction | 67.2% | Dec 2026 1 month to go | 1 month to go | 126 | 101 | +1.7% |
| Celia Homes | Under construction | 20% | Nov 2027 12 months to go | 12 months to go | 207 | 101 | +8.3% |
| The Corner | Under construction | 37.7% | Jun 2027 7 months to go | 7 months to go | 126 | 96 | +2% |
| Ag Square | Under construction | 68.8% | Sep 2026 1 month past it | 1 month past it | 372 | 95 | +9.2% |
| The V Tower | Completed | 100% | Sep 2023 | — | 369 | 93 | — |
| A 99 | Under construction | 47.8% | Oct 2026 This month | This month | 90 | 89 | — |
| Cove Living Residence By Imtiaz | Under construction | 47.2% | Apr 2027 5 months to go | 5 months to go | 744 | 88 | +2.1% |
| Rivo | Under construction | 7% | Dec 2027 13 months to go | 13 months to go | 133 | 83 | +0.5% |
| Samana Avenue | Under construction | 31.8% | Dec 2027 13 months to go | 13 months to go | 165 | 82 | — |
| Celesto Tower 2 | Not started | 0% | Jun 2028 19 months to go | 19 months to go | 231 | 80 | -1.6% |
| Marquis Vista | Under construction | 3.5% | Dec 2027 13 months to go | 13 months to go | 129 | 77 | +2.7% |
| DURAR1 | Completed | 100% | Oct 2013 | — | 241 | 75 | — |
| Khk 31 | Under construction | 25.8% | Mar 2027 4 months to go | 4 months to go | 160 | 73 | — |
| Cove Edition Residence 1 By Imtiaz | Under construction | 90.2% | Aug 2026 2 months past it | 2 months past it | 182 | 71 | — |
| Desert Sun Tower | Completed | 100% | Jun 2015 | — | 181 | 70 | — |
| Coventry Gardens | Under construction | 1.2% | Mar 2027 4 months to go | 4 months to go | 97 | 68 | -6.1% |
| Forest City Tower 2 | Under construction | 1.2% | Jun 2027 7 months to go | 7 months to go | 194 | 68 | +0.5% |
| Time 1 | Completed | 100% | Dec 2022 | — | 286 | 68 | +43% |
| Solanki One | Under construction | 35.2% | May 2028 18 months to go | 18 months to go | 133 | 67 | -0.2% |
Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Units not yet completed, by DLD end year
95 phases| DLD end year | Projects | Units |
|---|---|---|
| 2026 | 13 | 2,331 |
| 2027 | 39 | 8,747 |
| 2028 | 30 | 8,555 |
| 2029 | 8 | 3,144 |
| 2030 | 1 | 565 |
| No end date | 4 | 922 |
Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.
More on Dubai Land Residence Complex
Own a unit in one of these phases? Track it free
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology