DLD project no. 1875Completed43 units
Bright Corner برايت كورنر Completed 29 September 2019 (DLD) · DLD end date Sep 2019 · DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.
Completed projects cannot be added to My units.
CompletionDLD readings of % built, beside the share of the planned period gone
% built
28 October 2026| Date | % built | Source |
|---|---|---|
| 29 September 2019 | 100% | DLD inspection |
| 28 August 2018 | 94.8% | DLD inspection |
| 7 January 2018 | 60.4% | DLD inspection |
Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 5 August 2022, 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗
Site timeline
± 6 monthsEach date is ± 6 months. This is our reading, not DLD's; no image is shown. Read from imagery dated 5 July 2014 to 25 May 2026; method imagery-v1.
Registered period and actual build
Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.
Changes in the DLD register
No change to the end date, status or % built across the register exports we hold.
Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.
Building permits
1 of 1 buildingsBuildings on the project’s plots: 1, on construction permits: 1, as Dubai Municipality lists them.
Furthest stage reached: Final works.
| Work stage | Buildings |
|---|---|
| Final works | 1 |
Source: Dubai Municipality building permits, export of 26 October 2026. These dates and stages are Dubai Municipality’s records, not DLD’s register.
DLD registration
DLD services ↗Also registered: shops and showrooms 3.
Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.
Description in the DLD register: One Building, G+4+R1 includes 40 residential units and 3 retail shops and swimming pool and GYM with external and internal finishes
DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae
Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.
AED · sqft
No off-plan sales are registered for this project since 2020, so there is no launch price.
Prices are over apartments, the type most sales in this project are.
Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.
Median AED/sqft by quarter
2020-Q1 → 2025-Q4| Quarter | Registered sales | Median AED/sqft | DLD area Nad Al Shiba First |
|---|---|---|---|
| 2020-Q1 | 1 (off-plan 0, ready 1) | — | 792 |
| 2020-Q4 | 20 (off-plan 0, ready 20) | 1,001 | 1,000 |
| 2025-Q4 | 1 (off-plan 0, ready 1) | — | 1,596 |
Median AED/sqft of registered sales per quarter (apartments). Source: DLD. Grey dashed line: DLD area Nad Al Shiba First, median AED/sqft of ready sales of apartments by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.
Registered sales per quarter
| Quarter | Registered sales | Median AED/sqft | DLD area Nad Al Shiba First |
|---|---|---|---|
| 2020-Q1 | 1 (off-plan 0, ready 1) | — | 792 |
| 2020-Q4 | 20 (off-plan 0, ready 20) | 1,001 | 1,000 |
| 2025-Q4 | 1 (off-plan 0, ready 1) | — | 1,596 |
Registered sales per quarter, off-plan and ready units. Source: DLD.
Rents and gross yield
New Ejari rent contracts for apartments in this project, 12 months to 5 November 2026, against the 12 months before. Fewer than 10 ready sales per bedroom count in those 12 months, so no yield is shown.
| Bedrooms | Median annual rent | New contracts | Change on a year earlier |
|---|---|---|---|
| 2 BR | AED 100,000 | 8 | 0% |
New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.
Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.
Registered sales
The newest sales DLD has registered in this project, as DLD publishes them.
| Date | Market | Type | Size (sqft) | Price (AED) | AED/sqft |
|---|---|---|---|---|---|
| 1 December 2025 | ready | Apartment · 1 BR | 397 | 465,000 | 1,171 |
| 10 December 2020 | ready | Apartment · 2 BR | 1,107 | 1,107,070 | 1,000 |
| 10 December 2020 | ready | Apartment · 1 BR | 793 | 797,390 | 1,006 |
| 7 December 2020 | ready | Apartment · 2 BR | 2,501 | 1,655,290 | 662 |
| 7 December 2020 | ready | Apartment · 2 BR | 1,247 | 1,250,000 | 1,002 |
| 7 December 2020 | ready | Apartment · 2 BR | 1,244 | 1,250,000 | 1,005 |
| 7 December 2020 | ready | Apartment · 2 BR | 1,247 | 1,247,430 | 1,000 |
| 7 December 2020 | ready | Apartment · 2 BR | 1,107 | 1,107,070 | 1,000 |
| 7 December 2020 | ready | Apartment · 2 BR | 1,107 | 1,107,000 | 1,000 |
| 7 December 2020 | ready | Apartment · 1 BR | 909 | 910,000 | 1,001 |
Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.
Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence
LocationNadd Al Shiba First · Dubai Municipality community
Places near the project
Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.
School ratings: KHDA’s school directory ↗ · Report a wrong location
Dubai Municipality · Makani · © OpenStreetMap contributors · RTA
New homes within 1.5 km
Open projects within 1.5 km of the pin: 17, with 3,221 units and villas.
| DLD end year | Projects | Units and villas |
|---|---|---|
| 2018 | 1 | 36 |
| 2024 | 1 | 0 |
| 2025 | 3 | 508 |
| 2027 | 10 | 1,146 |
| 2028 | 1 | 1,453 |
| 2029 | 1 | 78 |
Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.
Open projects in Nadd Al Shiba First: 36
Open projects in the same DLD area, by registered sales in 24 months.
| Project | Built | DLD end date | AED/sqft, 12 mo | Sales, 24 mo |
|---|---|---|---|---|
| Maybach Six | 0% | Aug 2027 | 3,521 | 1,099 |
| Maybach Ultimate Luxury | 0% | Aug 2027 | 3,653 | 276 |
| Tonino Lamborghini Residences | 60% | Dec 2026 | — | 245 |
| Project Maybach | 0% | Jun 2027 | 3,421 | 214 |
| Nad Al Sheba Gardens Phase 11 | 0.1% | Jul 2029 | 3,141 | 211 |
| Nad Al Sheba Gardens Phase 10 | 0.4% | Oct 2028 | — | 204 |
| Nad Al Sheba Gardens Phase 8 & 9 | 0.7% | Oct 2028 | 1,862 | 202 |
| Nad Al Sheba Gardens Phase 7 | 4% | Feb 2028 | 2,603 | 155 |
| Emerge Residences | 21.1% | Nov 2027 | 2,245 | 47 |
| Nad Al Sheba Gardens Phase 3 | 97% | Apr 2026 | 2,085 | 39 |
| Sukoon by Nuri | 46.8% | Dec 2026 | 1,885 | 36 |
| Woodland Crest | 1.4% | Jun 2027 | 2,239 | 33 |
AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.
Developer in DLD data Fandah Palace Development L.L.C · DLD developer no. 1174
Completed a month or more after their DLD end date: 0 of 1 completed projects with both dates. In 1 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.
Other projects in Meydan Racecourse Community
DLD lists 33 projects in the master project Meydan Racecourse Community.
Questions about Bright Corner
When was Bright Corner completed?
Bright Corner is recorded as completed on 29 September 2019 (DLD register of 1 November 2026).
Who is the developer of Bright Corner?
Fandah Palace Development L.L.C, as registered with DLD.
What is the DLD project number of Bright Corner?
1875.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error