Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 1875Completed43 units

Bright Corner برايت كورنر Nad Al Shiba First · Meydan Racecourse Community by Fandah Palace Development L.L.CAll phases of Meydan Racecourse Community Completed 29 September 2019 (DLD) DLD end date Sep 2019 DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.

Completed projects cannot be added to My units.

Completed
Sep 2019
DLD end date Sep 2019
Build time
37 months
Sep 2016 → Sep 2019
Latest sales
—
Fewer than 5 recent sales
2 BR rent
100,000 AED/yr
8 leases, 12 months
Developer
1 project
1 completed · 43 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built

28 October 2026
Built
100%
Latest DLD register reading: 100% built on 28 October 2026 (register readings: 3). Latest DLD inspection: 100% built on 29 September 2019 (inspections: 3).
Every DLD inspection and every change in the register %, newest first
Date % built Source
29 September 2019 100% DLD inspection
28 August 2018 94.8% DLD inspection
7 January 2018 60.4% DLD inspection

Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 5 August 2022, 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗

Site timeline

± 6 months
Works startedSep 2016 ± 6 months
Structure risingApr 2017 ± 6 months
Topped outJul 2018 ± 6 months
FinishedDec 2020 ± 6 months

Each date is ± 6 months. This is our reading, not DLD's; no image is shown. Read from imagery dated 5 July 2014 to 25 May 2026; method imagery-v1.

Registered period and actual build

Registered period
37 monthsActual build
37 months
Start date
1 September 2016
DLD end date
29 September 2019
Completion date
29 September 2019
Completion vs DLD end date
On the date

Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.

Changes in the DLD register

No change to the end date, status or % built across the register exports we hold.

Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.

Building permits

1 of 1 buildings

Buildings on the project’s plots: 1, on construction permits: 1, as Dubai Municipality lists them.

Furthest stage reached: Final works.

Work not started
Site works
Foundations
Structure
Masonry
Finishes
Final works
Completed
Buildings
1
1 on construction permits
Permit status
Closed
259576
Issued
1 August 2016
Work start
5 August 2016
Completion
20 December 2018
Consultant · contractor
ART ARCHITECTURAL CONSULTANTS · D E C O BUILDING CONTRACTING L.L.C
Buildings by the furthest work stage Dubai Municipality lists
Work stage Buildings
Final works1

Source: Dubai Municipality building permits, export of 26 October 2026. These dates and stages are Dubai Municipality’s records, not DLD’s register.

DLD registration

DLD services ↗
DLD project number
1875
Escrow agent
Dubai Islamic Bank (Public Joint Stock Company)
Zoning authority
Dubai Municipality
Master project
Meydan Racecourse Community
DLD area
Nad Al Shiba First
Units · villas
43 · 0
Start → DLD end
Sep 2016 → Sep 2019
Registered units1 bed 18 · 2 bed 22; sizes 906–1,245 sqft

Also registered: shops and showrooms 3.

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: One Building, G+4+R1 includes 40 residential units and 3 retail shops and swimming pool and GYM with external and internal finishes

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft

No off-plan sales are registered for this project since 2020, so there is no launch price.

Prices are over apartments, the type most sales in this project are.

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Median AED/sqft by quarter

2020-Q1 → 2025-Q4

Median AED/sqft of registered sales per quarter (apartments). Source: DLD. Grey dashed line: DLD area Nad Al Shiba First, median AED/sqft of ready sales of apartments by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

Rents and gross yield

New Ejari rent contracts for apartments in this project, 12 months to 5 November 2026, against the 12 months before. Fewer than 10 ready sales per bedroom count in those 12 months, so no yield is shown.

Bedrooms Median annual rent New contracts Change on a year earlier
2 BR AED 100,000 8 0%

New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.

Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

The newest 10 of 1 registered sales in the 12 months to 5 November 2026
DateMarketType Size (sqft) Price (AED) AED/sqft
1 December 2025readyApartment · 1 BR 397 465,000 1,171
10 December 2020readyApartment · 2 BR 1,107 1,107,070 1,000
10 December 2020readyApartment · 1 BR 793 797,390 1,006
7 December 2020readyApartment · 2 BR 2,501 1,655,290 662
7 December 2020readyApartment · 2 BR 1,247 1,250,000 1,002
7 December 2020readyApartment · 2 BR 1,244 1,250,000 1,005
7 December 2020readyApartment · 2 BR 1,247 1,247,430 1,000
7 December 2020readyApartment · 2 BR 1,107 1,107,070 1,000
7 December 2020readyApartment · 2 BR 1,107 1,107,000 1,000
7 December 2020readyApartment · 1 BR 909 910,000 1,001

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

LocationNadd Al Shiba First · Dubai Municipality community

Day by 12 Grocery · 850 mPark · 850 mPark · 850 mPark · 860 mMOUNT WAY MINIMART · 1.1 kmBradosti Trading · 1.2 kmNorth London Collegiate School · 1.4 kmHartland International School · 1.5 kmProject location© OpenStreetMap contributors · Dubai Municipality · RTA · Makani
Project location Malls and supermarkets Schools and hospitals Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

Metro stationBurj Khalifa/ Dubai Mall Metro Station · Red Metro line · 5.5 km
MallSobha Mall (Under Construction) · 1.7 km
SupermarketDay by 12 Grocery · 850 m
HospitalHospital · 2 km
SchoolNorth London Collegiate School · 1.4 km
ParkPark · 850 m
BeachBeach · 2.8 km

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors · RTA

New homes within 1.5 km

Open projects within 1.5 km of the pin: 17, with 3,221 units and villas.

2018: 362024: 02025: 5082027: 1,1462028: 1,4532029: 78

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Nadd Al Shiba First: 36

Open projects in the same DLD area, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Maybach Six 0% Aug 2027 3,521 1,099
Maybach Ultimate Luxury 0% Aug 2027 3,653 276
Tonino Lamborghini Residences 60% Dec 2026 — 245
Project Maybach 0% Jun 2027 3,421 214
Nad Al Sheba Gardens Phase 11 0.1% Jul 2029 3,141 211
Nad Al Sheba Gardens Phase 10 0.4% Oct 2028 — 204
Nad Al Sheba Gardens Phase 8 & 9 0.7% Oct 2028 1,862 202
Nad Al Sheba Gardens Phase 7 4% Feb 2028 2,603 155
Emerge Residences 21.1% Nov 2027 2,245 47
Nad Al Sheba Gardens Phase 3 97% Apr 2026 2,085 39
Sukoon by Nuri 46.8% Dec 2026 1,885 36
Woodland Crest 1.4% Jun 2027 2,239 33

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Nadd Al Shiba First

Developer in DLD data Fandah Palace Development L.L.C · DLD developer no. 1174

Projects registered
1
1 completed · 0 under construction · 0 not started
Units delivered
43
0 in the pipeline

Completed a month or more after their DLD end date: 0 of 1 completed projects with both dates. In 1 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Other projects in Meydan Racecourse Community

DLD lists 33 projects in the master project Meydan Racecourse Community.

Royal ManorUnder construction · 77.8% · Dec 2018
Mews MansionsUnder construction · 55.6% · Dec 2025
Tonino Lamborghini ResidencesUnder construction · 60% · Dec 2026
Sukoon by NuriUnder construction · 46.8% · Dec 2026
Woodland CrestUnder construction · 1.4% · Jun 2027
Saddlewood ParkUnder construction · 12.5% · Sep 2027
Emerge ResidencesUnder construction · 21.1% · Nov 2027
Rabdan SquareUnder construction · 1.2% · Mar 2028
Tura ResidenceUnder construction · 0.7% · Apr 2029
Flamingo Lux ResidencePending · 47% · May 2025
Project MaybachNot started · 0% · Jun 2027
Maybach SixNot started · 0% · Aug 2027

Questions about Bright Corner

When was Bright Corner completed?

Bright Corner is recorded as completed on 29 September 2019 (DLD register of 1 November 2026).

Who is the developer of Bright Corner?

Fandah Palace Development L.L.C, as registered with DLD.

What is the DLD project number of Bright Corner?

1875.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error