DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 4539Not started463 units

Treppan Vision تريبان فيجن Wadi Al Safa 5 · Dubai Land Residence Complex by Fakhruddin Properties Development L.L.CAll phases of Dubai Land Residence Complex DLD status: Not started (DLD register as of 1 November 2026) DLD end date May 2029 30 months to go DLD register as of 1 November 2026. The end date is the one registered with DLD, not a handover forecast.

% built
0%
DLD register, 1 November 2026
Registered start
Jan 2027
DLD end date May 2029
Latest sales
—
Fewer than 5 recent sales
Developer
6 projects
0 completed · 0 units delivered

Completion

DLD status: Not started. 0% built, DLD end date 31 May 2029. DLD Project Status shows inspection reports once works begin.

DLD register readings
Date % built DLD end dateDLD status
28 October 2026 0% 31 May 2029Not started

Source: DLD projects register, export of 1 November 2026.

Inspection photos and reports

DLD’s Project Status service (Mashrooi) shows inspection details and site photos. Look the project up by its number.

CraneScore links to DLD and does not copy or host its photos or reports.

DLD registration

DLD services ↗
DLD project number
4539
Escrow agent
Emirates Nbd Bank (P.J.S.C)
Zoning authority
Dubai Development Authority (DDA)
Master project
Dubai Land Residence Complex
DLD area
Wadi Al Safa 5
Units · villas
463 · 0
Start → DLD end
Jan 2027 → May 2029
Registered unitsStudio 252 · 1 bed 108 · 2 bed 48; sizes 406–809 sqft

Also registered: offices 48 · shops and showrooms 7.

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: 2B+G+3P+14FL

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

LocationWadi Al Safa 5 · Dubai Municipality community

Shua Al Madina · 210 mWest zone fresh supermarket · 350 mKP Mart · 360 mGems First Point School (The Villa) · 670 mCentro Courtyard 11 · 890 mCentro Courtyard 10 · 1 kmCentro Courtyard 7 · 1.2 kmProject location© OpenStreetMap contributors · Dubai Municipality · Makani
Project location Malls and supermarkets Schools and hospitals Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

MallSilicon Central · 2.3 km
SupermarketShua Al Madina · 210 m
HospitalHLG Umar · 3.3 km
SchoolGems First Point School (The Villa) · 670 m
ParkCentro Courtyard 11 · 890 m
BeachBeach · 6 km

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors

New homes within 1.5 km

Open projects within 1.5 km of the pin: 98, with 23,860 units and villas.

2026: 2,3312027: 8,7472028: 8,6142029: 2,6812030: 565No end date: 922

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Wadi Al Safa 5: 108

Open projects in the same DLD area with a DLD end year from 2028 to 2030, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Peace Lagoons by Peace Homes 4.2% Sep 2028 1,410 795
Verdes by Haven 1 17.7% May 2028 1,374 658
Peace Lagoons II by Peace Homes 4% Jan 2029 1,585 553
Samana Boulevard Heights 2.5% Dec 2028 1,522 526
La Tilia at Villanova Phase 2 10.6% Aug 2028 1,487 477
La Tilia at Villanova Phase 1 13.8% Aug 2028 1,435 456
Samana IBIZA 5.5% Feb 2028 1,426 444
Samana Parkville 13.9% Sep 2028 1,503 419
Athlon By Al Dar 1 27.3% May 2028 1,574 387
Rise by Athlon 1 3.7% Dec 2029 1,657 356
Athlon By Al Dar 2 20.4% Sep 2028 1,577 314
Rise by Athlon 2 3.7% Jan 2030 1,678 308

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Wadi Al Safa 5

Developer in DLD data Fakhruddin Properties Development L.L.C · DLD developer no. 1415

Projects registered
6
0 completed · 4 under construction · 2 not started
Units delivered
0
1,793 in the pipeline
Past the DLD end date
1
of 4 under construction with a DLD end date

Fakhruddin Properties Development L.L.C is one of 2 DLD-registered developers we list together as Fakhruddin. See the group

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error