Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 4414Not started88 units

X11 X11 Madinat Al Mataar · Dubai South Residential District by Bamx Eleven Real Estate Development L.L.CAll phases of Dubai South Residential District DLD status: Not started (DLD register as of 1 November 2026) DLD end date Dec 2028 25 months to go DLD register as of 1 November 2026. The end date is the one registered with DLD, not a handover forecast.

% built
0%
DLD register, 1 November 2026
Registered start
Oct 2026
DLD end date Dec 2028
Latest sales
—
Fewer than 5 recent sales
Developer
1 project
0 completed · 0 units delivered

Completion

DLD status: Not started. 0% built, DLD end date 25 December 2028. DLD Project Status shows inspection reports once works begin.

DLD register readings
Date % built DLD end dateDLD status
28 October 2026 0% 25 December 2028Not started

Source: DLD projects register, export of 1 November 2026.

Inspection photos and reports

DLD’s Project Status service (Mashrooi) shows inspection details and site photos. Look the project up by its number.

CraneScore links to DLD and does not copy or host its photos or reports.

DLD registration

DLD services ↗
DLD project number
4414
Escrow agent
Abu Dhabi Commercial Bank
Zoning authority
Dubai South
Master project
Dubai South Residential District
DLD area
Madinat Al Mataar
Units · villas
88 · 0
Start → DLD end
Oct 2026 → Dec 2028
Registered units1 bed 32 · 2 bed 44 · 3 bed 12; sizes 766–1,068 sqft

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: Basement + Ground + 6 Floors + Roof

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft

Fewer than 5 sales with a size were registered in the first 90 days, so no launch price is shown.

Prices are over apartments, the type most sales in this project are.

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

Rents in DLD area Madinat Al Mataar

New Ejari rent contracts for apartments across DLD area Madinat Al Mataar, 12 months to 5 November 2026, against the 12 months before: the rent level around this project. No yield is shown before the project is completed.

Bedrooms Median annual rent New contracts Change on a year earlier
Studio AED 41,000 818 +2.5%
1 BR AED 56,500 1,084 +0.9%
2 BR AED 85,000 1,080 0%
3 BR AED 120,000 182 0%

New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.

Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

The newest 2 of 2 registered sales in the 12 months to 5 November 2026
DateMarketType Size (sqft) Price (AED) AED/sqft
4 November 2026off-planApartment · 2 BR 1,047 1,457,977 1,393
16 October 2026off-planApartment · 1 BR 621 973,421 1,568

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

Looking for a unit in this or similar projects?

Tell us what you are looking for in X11 or similar projects. We reply by e-mail, and your request stays with CraneScore.

We send a 6-digit code to confirm it.
Bedrooms

Estimated value range

Not enough registered off-plan sales for an estimate (at least 5 of one bedroom count in 12 months).

Automated estimate, not a valuation

Track this unit

Automated estimate from registered off-plan sales (developer sales and resales mixed); not a valuation by a registered valuer; not for mortgage or court use.

Payment scenarioEnter the developer’s plan to see what you pay and when. Handover starts at the DLD end date (Dec 2028); move it with the slider.

A scenario from your own inputs, not this project's verified payment plan.

Common plans

Plan shares add up to 100% (must be 100%).

Handover
Dec 2028
Paid by handover
AED 1,045,000
Fees included
Price paid at handover
100%
Total cost
AED 1,045,000
Fees: AED 45,000

Payments per quarter

AED

Payments per quarter, AED, fees included. Illustration from your inputs.

The DLD fee (4% of the price) and the fees above are paid at booking. With a resale price, the unit is sold at handover and the buyer takes over any unpaid balance; agent fees, mortgage costs and service charges are left out. An illustration from your inputs, not financial advice.

Mortgage for a unit here

Questions about financing a unit in X11? Leave your details and we reply by e-mail. Your request stays with CraneScore.

We send a 6-digit code to confirm it.

LocationMadinat Al Mataar · Dubai Municipality community

Supermarket · 250 mPark · 450 mProject location© OpenStreetMap contributors · Dubai Municipality · RTA · Makani
Project location Malls and supermarkets Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

Metro stationEXPO Metro Station · Red Metro line · 7.5 km
MallRijat Retail Mall-12 · 5.3 km
SupermarketSupermarket · 250 m
HospitalNMC dip · 9.4 km
ParkPark · 450 m

Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors · RTA

New homes within 1.5 km

Open projects within 1.5 km of the pin: 85, with 8,356 units and villas.

2019: 1082025: 1132026: 9202027: 1,4652028: 2,6612029: 2,7992030: 290No end date: 0

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Madinat Al Mataar: 167

Open projects in the same DLD area with a DLD end year from 2027 to 2029, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Azizi Venice 6 11.6% Dec 2027 2,032 1,302
Terra Heights 9.1% Mar 2029 1,994 1,017
Azizi Venice 15 0% May 2027 1,715 904
azizi venice 13 45.9% Sep 2027 1,675 797
azizi venice 12 21.6% Sep 2027 1,685 753
Azizi Venice 11 25.9% Aug 2027 1,667 696
Terra Gardens 0.1% Oct 2029 2,127 544
South Square 2.6% Jun 2028 1,473 428
Expo City Sidr Residences 25% Mar 2028 2,088 423
Windsor House 3.1% Jul 2029 1,458 399
Windsor House Ii 0.6% Jul 2029 1,564 392
Azizi Venice 16 0% Jun 2027 1,898 310

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Madinat Al Mataar

Developer in DLD data Bamx Eleven Real Estate Development L.L.C · DLD developer no. 2596

Projects registered
1
0 completed · 0 under construction · 1 not started
Units delivered
0
88 in the pipeline

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error