DLD project no. 4305Under construction72 units
RR Grand ار ار جراند 10.2% built (DLD register as of 1 November 2026) · DLD end date Apr 2027 · 5 months to go DLD register as of 1 November 2026. The end date is the one registered with DLD, not a handover forecast.
CompletionDLD readings of % built, beside the share of the planned period gone
% built and period elapsed
1 November 2026Two separate measures: one is DLD's % built, the other is time on the calendar.
| Date | % built | Source |
|---|---|---|
| 20 January 2026 | 10.2% | DLD inspection |
Source: Dubai Land Department projects register, as of 1 November 2026. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗ Period elapsed: our calculation from DLD’s start and end dates.
Our completion calculation
Pace since the last two DLD readings: —
Our calculation from DLD readings. It describes the recent pace only; it is not a forecast of the completion date.
Site timeline
± 6 monthsEach date is ± 6 months. This is our reading, not DLD's; no image is shown. Read from imagery dated 28 April 2023 to 15 March 2025; method imagery-v1.
Changes in the DLD register
Source: DLD projects register exports, compared by CraneScore. Dates and progress are those in the Dubai Land Department projects register on each register date, not inspection dates. DLD can revise the end date; we keep every register reading from 28 October 2026 on and list the changes here.
Inspection photos and reports
DLD’s Project Status service (Mashrooi) shows inspection details and site photos. Look the project up by its number.
CraneScore links to DLD and does not copy or host its photos or reports.
DLD registration
DLD services ↗Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.
Description in the DLD register: G+4
DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae
Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.
AED · sqft
Fewer than 5 sales with a size were registered in the first 90 days, so no launch price is shown.
Prices are over apartments, the type most sales in this project are.
Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.
Registered sales per quarter
| Quarter | Registered sales |
|---|---|
| 2026-Q4 | 1 (off-plan 1, ready 0) |
Registered sales per quarter, off-plan and ready units. Source: DLD.
Rents in DLD area Madinat Al Mataar
New Ejari rent contracts for apartments across DLD area Madinat Al Mataar, 12 months to 5 November 2026, against the 12 months before: the rent level around this project. No yield is shown before the project is completed.
| Bedrooms | Median annual rent | New contracts | Change on a year earlier |
|---|---|---|---|
| Studio | AED 41,000 | 818 | +2.5% |
| 1 BR | AED 56,500 | 1,084 | +0.9% |
| 2 BR | AED 85,000 | 1,080 | 0% |
| 3 BR | AED 120,000 | 182 | 0% |
New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.
Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.
Registered sales
The newest sales DLD has registered in this project, as DLD publishes them.
| Date | Market | Type | Size (sqft) | Price (AED) | AED/sqft |
|---|---|---|---|---|---|
| 5 November 2026 | off-plan | Apartment · 1 BR | 691 | 889,368 | 1,287 |
Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.
Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence
Looking for a unit in this or similar projects?
Tell us what you are looking for in RR Grand or similar projects. We reply by e-mail, and your request stays with CraneScore.
Estimated value range
Not enough registered off-plan sales for an estimate (at least 5 of one bedroom count in 12 months).
Automated estimate from registered off-plan sales (developer sales and resales mixed); not a valuation by a registered valuer; not for mortgage or court use.
Payment scenarioEnter the developer’s plan to see what you pay and when. Handover starts at the DLD end date (Apr 2027); move it with the slider.
A scenario from your own inputs, not this project's verified payment plan.
Common plans
Plan shares add up to 100% (must be 100%).
Payments per quarter
AED| Quarter | Paid |
|---|---|
| 2026-Q4 | AED 345,000 · AED 345,000 paid so far |
| 2027-Q1 | AED 300,000 · AED 645,000 paid so far |
| 2027-Q2 | AED 400,000 · AED 1,045,000 paid so far |
Payments per quarter, AED, fees included. Illustration from your inputs.
The DLD fee (4% of the price) and the fees above are paid at booking. With a resale price, the unit is sold at handover and the buyer takes over any unpaid balance; agent fees, mortgage costs and service charges are left out. An illustration from your inputs, not financial advice.
Mortgage for a unit here
Questions about financing a unit in RR Grand? Leave your details and we reply by e-mail. Your request stays with CraneScore.
LocationMadinat Al Mataar · Dubai Municipality community
Places near the project
Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.
Dubai Municipality · Makani · © OpenStreetMap contributors · RTA
New homes within 1.5 km
Open projects within 1.5 km of the pin: 86, with 8,222 units and villas.
| DLD end year | Projects | Units and villas |
|---|---|---|
| 2019 | 1 | 108 |
| 2025 | 2 | 113 |
| 2026 | 16 | 954 |
| 2027 | 28 | 1,530 |
| 2028 | 26 | 2,749 |
| 2029 | 11 | 2,478 |
| 2030 | 1 | 290 |
| No end date | 1 | 0 |
Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.
Open projects in Madinat Al Mataar: 167
Open projects in the same DLD area with a DLD end year from 2026 to 2028, by registered sales in 24 months.
| Project | Built | DLD end date | AED/sqft, 12 mo | Sales, 24 mo |
|---|---|---|---|---|
| Azizi Venice 14 | 30.3% | May 2026 | 1,649 | 2,546 |
| Azizi Venice 6 | 11.6% | Dec 2027 | 2,032 | 1,302 |
| Azizi Venice 7 | 29.2% | Jan 2026 | 1,849 | 1,180 |
| Azizi Venice 15 | 0% | May 2027 | 1,715 | 904 |
| azizi venice 13 | 45.9% | Sep 2027 | 1,675 | 797 |
| azizi venice 12 | 21.6% | Sep 2027 | 1,685 | 753 |
| Azizi Venice 11 | 25.9% | Aug 2027 | 1,667 | 696 |
| South Square | 2.6% | Jun 2028 | 1,473 | 428 |
| Expo City Sidr Residences | 25% | Mar 2028 | 2,088 | 423 |
| Azizi Venice 16 | 0% | Jun 2027 | 1,898 | 310 |
| Expo City Al Waha Residences 01 | 65.8% | Jun 2027 | 2,515 | 286 |
| Expo City Al Waha Residences 02 | 61.4% | Jun 2027 | 2,550 | 273 |
AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.
Developer in DLD data Red Rose Properties L.L.C · DLD developer no. 1462
Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.
Other projects in Dubai South Residential District
DLD lists 119 projects in the master project Dubai South Residential District.
Questions about RR Grand
When is RR Grand's handover?
DLD lists an end date of Apr 2027 (register of 1 November 2026); the SPA sets the handover terms.
Is RR Grand past its DLD end date?
No. Its DLD end date is Apr 2027, 5 months after the register of 1 November 2026.
How far along is RR Grand?
10.2% built in the DLD register of 1 November 2026.
Who is the developer of RR Grand?
Red Rose Properties L.L.C, as registered with DLD.
What is the DLD project number of RR Grand?
4305.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error