DLD project no. 1336Completed289 units
The Address Residence Fountain Views II إطلالات على نافورة العنوان II Completed 22 July 2019 (DLD) · DLD end date Jul 2019 · DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.
Completed projects cannot be added to My units.

CompletionDLD readings of % built, beside the share of the planned period gone
% built
28 October 2026| Date | % built | Source |
|---|---|---|
| 4 July 2019 | 100% | DLD inspection |
| 22 May 2019 | 98.3% | DLD inspection |
| 16 January 2019 | 91.5% | DLD inspection |
| 30 August 2018 | 86.1% | DLD inspection |
| 9 April 2018 | 83.4% | DLD inspection |
| 18 December 2017 | 80.4% | DLD inspection |
| 17 August 2017 | 71.1% | DLD inspection |
| 26 April 2017 | 57.2% | DLD inspection |
| 13 November 2016 | 50% | DLD inspection |
| 21 June 2016 | 42.6% | DLD inspection |
| 27 December 2015 | 32.1% | DLD inspection |
| 12 February 2015 | 24.2% | DLD inspection |
| 26 May 2014 | 8.7% | DLD inspection |
Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 5 August 2022, 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗
Site timeline
± 6 monthsOur imagery reading holds no milestone for this project yet.
Our reading of historical satellite imagery
Registered period and actual build
Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.
Changes in the DLD register
No change to the end date, status or % built across the register exports we hold.
Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.
Building permits
2 of 9 buildingsBuildings on the project’s plots: 9, on construction permits: 3, as Dubai Municipality lists them.
Furthest stage reached: Completed.
| Work stage | Buildings |
|---|---|
| Work not started | 1 |
| Final works | 4 |
| Completed | 2 |
| No stage listed | 2 |
Source: Dubai Municipality building permits, export of 26 October 2026. These dates and stages are Dubai Municipality’s records, not DLD’s register.
DLD registration
DLD services ↗Homes: hotel apartments and rooms 289.
Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.
Description in the DLD register: PROJECT CONSISTS OF 3B+G+M+10P+59 RESIDENTIAL BUILDING LOCATED IN BURJ KHALIFA. THE APARTMENTS ARE DESIGNED TO HAVE A CONCRETE STRUCTURE AND BLOCK WITH INTERNAL AND EXTERNAL FINISHES.
DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae
Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.
AED · sqft
No off-plan sales are registered for this project since 2020, so there is no launch price.
Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.
Service charges
What owners pay a year in completed buildings of the project’s master community, from their owners’ association budgets. A building’s own charge is set by its own budget.
Median AED per sq ft a year of residential owners’ association budgets, each development counted once, in the newest budget year with at least 10 developments. Plots, shared areas and hotel rooms are left out. A budget is not any one owner’s bill.
Source: Dubai Land Department, owners’ association budgets (service charges).
LocationBurj Khalifa · Dubai Municipality community
Places near the project
Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.
School ratings: KHDA’s school directory ↗ · Report a wrong location
Dubai Municipality · Makani · © OpenStreetMap contributors · RTA
New homes within 1.5 km
Open projects within 1.5 km of the pin: 28, with 8,238 units and villas.
| DLD end year | Projects | Units and villas |
|---|---|---|
| 2023 | 1 | 145 |
| 2025 | 3 | 105 |
| 2026 | 6 | 2,427 |
| 2027 | 11 | 2,919 |
| 2029 | 2 | 960 |
| 2030 | 1 | 119 |
| 2031 | 1 | 484 |
| No end date | 3 | 1,079 |
Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.
Open projects in Burj Khalifa: 19
Open projects in the same DLD area, by registered sales in 24 months.
| Project | Built | DLD end date | AED/sqft, 12 mo | Sales, 24 mo |
|---|---|---|---|---|
| Binghatti Skyblade | 17.1% | Nov 2027 | 3,927 | 567 |
| The St. Regis Residences, Downtown Dubai | 76.1% | Dec 2026 | 3,118 | 369 |
| One Residence | 6.3% | Mar 2027 | 2,931 | 250 |
| Solara Tower Dubai | 20.7% | Aug 2027 | 3,737 | 165 |
| Euphoric Residences | 8.3% | Dec 2027 | 3,240 | 98 |
| City Center Residences | 72.3% | Sep 2026 | 2,667 | 77 |
| Baccarat Hotel and Residences, Dubai | 21.2% | Dec 2026 | 5,711 | 71 |
| Mercedes-Benz Places | Binghatti | 65.3% | Dec 2026 | 5,136 | 67 |
| Address Grand Downtown | 10.8% | Jun 2028 | — | 60 |
| Volta Tower | 29.3% | Dec 2027 | 2,394 | 57 |
| Azha Downtown Residences | 27% | Aug 2027 | 2,439 | 42 |
| ROVE HOME RESIDENCES by IRTH | 62.7% | Apr 2026 | 3,371 | 40 |
AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.
Developer in DLD data Emaar Development P.J.S.C. · DLD developer no. 1211
Completed a month or more after their DLD end date: 0 of 57 completed projects with both dates. In 38 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
Emaar Development P.J.S.C. is one of 7 DLD-registered developers we list together as Emaar. See the group
Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.
Other projects in DownTown Dubai
DLD lists 59 projects in the master project DownTown Dubai.
Questions about The Address Residence Fountain Views II
When was The Address Residence Fountain Views II completed?
The Address Residence Fountain Views II is recorded as completed on 22 July 2019 (DLD register of 1 November 2026).
Who is the developer of The Address Residence Fountain Views II?
Emaar Development P.J.S.C., as registered with DLD.
What is the DLD project number of The Address Residence Fountain Views II?
1336.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error