DLD master projectBurj Khalifa
DownTown Dubai 16 of 60 phases not yet completed · 4,860 units · 4,843 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026
DownTown Dubai has 60 projects in the Dubai Land Department projects register as of 1 November 2026: 16 not yet completed, with 4,860 units and villas. By DLD status: Under construction 12 · Completed 44 · Pending 4. Under construction and past the DLD end date: 2.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Map of the phasesThe map shows 60 of the 60 phases: those with a map pin. Pins mark approximate locations.
Burj Khalifa (DM community)
Phases (60)Ordered by registered sales over 24 months
| Project | DLD status | Built | DLD end date / completion | To DLD end date | Units | Sales, 24 mo | Since launch |
|---|---|---|---|---|---|---|---|
| Binghatti Skyblade | Under construction | 17.1% | Nov 2027 12 months to go | 12 months to go | 596 | 567 | +0.1% |
| The St. Regis Residences, Downtown Dubai | Under construction | 76.1% | Dec 2026 1 month to go | 1 month to go | 1,108 | 369 | +13.6% |
| One Residence | Under construction | 6.3% | Mar 2027 4 months to go | 4 months to go | 458 | 250 | +9.3% |
| Burj Khalifa Towers | Completed | 100% | Jan 2012 | — | 1,078 | 248 | — |
| Grande | Completed | 100% | Jun 2022 | — | 906 | 210 | — |
| Forte | Completed | 100% | Nov 2022 | — | 927 | 194 | — |
| The Address Dubai Opera | Completed | 100% | Mar 2023 | — | 873 | 180 | — |
| 29 Boulevard | Completed | 100% | Apr 2013 | — | 750 | 169 | — |
| Solara Tower Dubai | Under construction | 20.7% | Aug 2027 9 months to go | 9 months to go | 231 | 165 | +11.2% |
| Act One | Act Two | Completed | 100% | Jan 2022 | — | 787 | 152 | — |
| Burj Views | Completed | 100% | Sep 2009 | — | 737 | 140 | — |
| Burj Crown | Completed | 100% | Aug 2023 | — | 433 | 111 | — |
| Boulevard Point | Completed | 100% | Dec 2019 | — | 449 | 109 | — |
| Burj Royale | Completed | 100% | Oct 2022 | — | 602 | 99 | — |
| Euphoric Residences | Under construction | 8.3% | Dec 2027 13 months to go | 13 months to go | 276 | 98 | — |
| Imperial Avenue | Completed | 100% | Jun 2025 | — | 431 | 96 | — |
| Burj Vista | Completed | 100% | Apr 2017 | — | 790 | 95 | — |
| Dd Stand Point | Completed | 100% | Dec 2012 | — | 537 | 92 | — |
| The Dubai Mall | Completed | 100% | Aug 2008 | — | 456 | 92 | — |
| Dd Boulevard Central | Completed | 100% | Aug 2012 | — | 424 | 79 | — |
| Elite Downtown Residence | Completed | 100% | Feb 2022 | — | 469 | 79 | — |
| Blvd Heights | Completed | 100% | Apr 2020 | — | 558 | 78 | — |
| City Center Residences | Under construction | 72.3% | Sep 2026 1 month past it | 1 month past it | 384 | 77 | +9.7% |
| The Signature | Completed | 100% | May 2013 | — | 356 | 75 | — |
| Baccarat Hotel and Residences, Dubai | Under construction | 21.2% | Dec 2026 1 month to go | 1 month to go | 98 | 71 | — |
| Bellevue Towers | Completed | 100% | Jul 2020 | — | 365 | 71 | — |
| Burj Al Nujoom | Completed | 100% | Sep 2013 | — | 408 | 68 | — |
| Mercedes-Benz Places | Binghatti | Under construction | 65.3% | Dec 2026 1 month to go | 1 month to go | 163 | 67 | -13.8% |
| Claren 1 | Completed | 100% | Jul 2012 | — | 321 | 61 | — |
| Society House Downtown Dubai | Completed | 100% | Sep 2026 | — | 417 | 59 | -1.1% |
| Blvd Crescent | Completed | 100% | Jul 2018 | — | 365 | 55 | — |
| Opera Grand | Completed | 100% | Dec 2021 | — | 306 | 53 | — |
| Exquisite Living Residences | Completed | 100% | Jul 2026 | — | 234 | 49 | +7.2% |
| Azha Downtown Residences | Under construction | 27% | Aug 2027 9 months to go | 9 months to go | 73 | 42 | — |
| Mada Residences Tower | Completed | 100% | Jun 2018 | — | 193 | 41 | — |
| ROVE HOME RESIDENCES by IRTH | Under construction | 62.7% | Apr 2026 6 months past it | 6 months past it | 349 | 40 | +4% |
| Opulent Residences | Under construction | 8.5% | Dec 2027 13 months to go | 13 months to go | 230 | 38 | — |
| Vida Dubai Mall | Completed | 100% | Feb 2022 | — | 621 | 37 | — |
| Inaura Hotels & Residences | Under construction | 1.3% | Jun 2030 43 months to go | 43 months to go | 119 | 36 | +0.7% |
| Il PRIMO | Completed | 100% | Dec 2022 | — | 137 | 33 | — |
| Dt 1 | Completed | 100% | Mar 2020 | — | 133 | 33 | — |
| Rp Heights | Completed | 100% | Apr 2020 | — | 296 | 32 | — |
| The Distinction | Completed | 100% | Feb 2016 | — | 308 | 31 | — |
| Upper Crest | Completed | 100% | Dec 2015 | — | 397 | 26 | — |
| Bahwan Tower | Completed | 100% | Sep 2018 | — | 135 | 24 | — |
| Elegance Tower | Completed | 100% | Sep 2026 | — | 296 | 23 | — |
| Mon Reve | Completed | 100% | Nov 2015 | — | 97 | 13 | — |
| The 118 | Completed | 100% | Apr 2016 | — | 28 | 11 | — |
| THE RESIDENCE | Burj Khalifa | Completed | 100% | Sep 2026 | — | 35 | 5 | — |
| Project 2983, Burj Khalifa | Pending | 48.3% | Dec 2025 10 months past it | 10 months past it | 0 | 0 | — |
| Banyan Tree Residences Aurelia Dubai | Pending | 0% | Dec 2025 10 months past it | 10 months past it | 33 | 0 | — |
| Sunteck MAS | Pending | 0% | Jun 2031 55 months to go | 55 months to go | 484 | 0 | — |
| Cityview Residences | Pending | 0% | Mar 2030 40 months to go | 40 months to go | 258 | 0 | — |
| BD Boulevard Plaza | Completed | 100% | Feb 2012 | — | 217 | 0 | — |
| The Address - The Blvd | Completed | 100% | Mar 2017 | — | 543 | 0 | — |
| The Address Residence-Fountain Views | Completed | 100% | Jan 2019 | — | 286 | 0 | — |
| The Address Residence Fountain Views II | Completed | 100% | Jul 2019 | — | 289 | 0 | — |
| The Address Residence - Sky View | Completed | 100% | Sep 2019 | — | 708 | 0 | — |
| The Address Residence Fountain Views III | Completed | 100% | Dec 2016 | — | 209 | 0 | — |
| Vida Residence Downtown Dubai | Completed | 100% | May 2018 | — | 347 | 0 | — |
Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Units not yet completed, by DLD end year
16 phases| DLD end year | Projects | Units |
|---|---|---|
| 2025 | 2 | 33 |
| 2026 | 5 | 2,102 |
| 2027 | 6 | 1,864 |
| 2030 | 2 | 377 |
| 2031 | 1 | 484 |
Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.
More on DownTown Dubai
Own a unit in one of these phases? Track it free
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology