DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD master projectNadd Al Shiba First

Nad Al Sheba Gardens 9 of 14 phases not yet completed · 899 units · 290 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026

Nad Al Sheba Gardens has 14 projects in the Dubai Land Department projects register as of 1 November 2026: 9 not yet completed, with 899 units and villas. By DLD status: Completed 5 · Under construction 8 · Pending 1. Under construction and past the DLD end date: 4.

Phases
14
5 completed
Not yet completed
9
8 under construction
Units not yet completed
899
units and villas · 682
Sales, 24 mo
290
registered with DLD

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Map of the phasesThe map shows 14 of the 14 phases: those with a map pin. Pins mark approximate locations.

Solcasa Residence · Completed · Project locationThe Roof Residence · Completed · Project locationNad Al Sheba Gardens Phase 3 · Under construction · Approximate project locationNad AL Sheba Gardens Phase 4 · Under construction · Approximate project locationLa Vue Parc · Under construction · Project locationEthan · Under construction · Project locationNad Al Sheba Gardens Phase 5 · Under construction · Approximate project locationCelia gardens · Completed · Project locationOne By Nine · Under construction · Project locationNad Al Sheba Gardens Phase 6 · Under construction · Approximate project locationQueen's Garden · Under construction · Project locationNad Al Sheba Gardens Phase 2 · Completed · Approximate project locationMag 22 · Completed · Project locationProject 2906, Nad Al Shiba First · Pending · Project locationDubai Municipality · Makani
Under construction Pending Completed Approximate project locations

Nadd Al Shiba First (DM community)

Phases (14)Ordered by registered sales over 24 months

Phases (14)
ProjectDLD status Built DLD end date / completion To DLD end date Units Sales, 24 mo Since launch
Solcasa ResidenceCompleted 100% Oct 2026 — 58 48 —
The Roof ResidenceCompleted 100% Feb 2026 — 68 45 -1.3%
Nad Al Sheba Gardens Phase 3Under construction 97% Apr 2026 6 months past it 6 months past it 235 39 +26.6%
Nad AL Sheba Gardens Phase 4Under construction 76.3% — — 188 26 -10.3%
La Vue ParcUnder construction 15.4% Sep 2027 10 months to go 10 months to go 46 25 —
EthanUnder construction 63.7% Jun 2026 4 months past it 4 months past it 48 23 —
Nad Al Sheba Gardens Phase 5Under construction 37.5% — — 159 21 +9.4%
Celia gardensCompleted 100% Sep 2026 — 44 19 —
One By NineUnder construction 50.3% Nov 2025 11 months past it 11 months past it 46 12 —
Nad Al Sheba Gardens Phase 6Under construction 13.9% — — 100 9 -12.8%
Queen's GardenUnder construction 42.2% Aug 2026 3 months past it 3 months past it 77 8 —
Nad Al Sheba Gardens Phase 2Completed 100% Dec 2025 — 212 8 —
Mag 22Completed 100% Jan 2025 — 22 7 —
Project 2906, Nad Al Shiba FirstPending 0% — — 0 0 —

Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Units not yet completed, by DLD end year

9 phases
2025: 462026: 3602027: 46No end date: 447

Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.

More on Nad Al Sheba Gardens

Own a unit in one of these phases? Track it free

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology