DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 1392Completed

Arabian RANCHES- Rosa Community المرابع العربية - روزا Wadi Al Safa 7 · Arabian Ranches II - ROSA by Emaar Properties (P.J.S.C) Completed 15 October 2016 (DLD) DLD end date Oct 2016 DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.

Completed projects cannot be added to My units.

Completed
Oct 2016
DLD end date Oct 2016
Build time
22 months
Dec 2014 → Oct 2016
Latest sales
—
Fewer than 5 recent sales
4 BR rent
400,000 AED/yr
16 leases, 12 months
Developer
61 projects
53 completed · 13,771 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built

28 October 2026
Built
100%
Latest DLD register reading: 100% built on 28 October 2026 (register readings: 3). Latest DLD inspection: 100% built on 12 July 2017 (inspections: 8).
Every DLD inspection and every change in the register %, newest first
Date % built Source
12 July 2017 100% DLD inspection
8 May 2017 98.1% DLD inspection
5 December 2016 95.1% DLD inspection
21 September 2016 90.1% DLD inspection
11 May 2016 52% DLD inspection
25 February 2016 41% DLD inspection
7 September 2015 14.1% DLD inspection
22 December 2014 4.4% DLD inspection

Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 5 August 2022, 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗

Site timeline

± 6 months

Our imagery reading holds no milestone for this project yet.

Our reading of historical satellite imagery

Registered period and actual build

Registered period
22 monthsActual build
22 months
Start date
1 December 2014
DLD end date
15 October 2016
Completion date
15 October 2016
Completion vs DLD end date
On the date

Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.

Changes in the DLD register

No change to the end date, status or % built across the register exports we hold.

Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.

DLD registration

DLD services ↗
DLD project number
1392
Escrow agent
Dubai Islamic Bank (Public Joint Stock Company)
Zoning authority
Dubai Development Authority (DDA)
Master project
Arabian Ranches II - ROSA
DLD area
Wadi Al Safa 7
Units · villas
0 · 0
Start → DLD end
Dec 2014 → Oct 2016
Registered units4 bed 94 · 5+ bed 50; sizes 4,318–5,370 sqft

Homes: villas 144.

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: The Project consists of 144 nos. G+1 Villas located in Wadi Al Safa 7, Dubai UAE. The villas are designed to have a concrete structure and block with internal and external finishes.

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft

No off-plan sales are registered for this project since 2020, so there is no launch price.

Prices are over villas and townhouses, the type most sales in this project are.

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Median AED/sqft by quarter

2020-Q3 → 2026-Q1

Median AED/sqft of registered sales per quarter (villas and townhouses). Source: DLD. Grey dashed line: DLD area Wadi Al Safa 7, median AED/sqft of ready sales of villas and townhouses by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

Rents and gross yield

New Ejari rent contracts for villas and townhouses in this project, 12 months to 5 November 2026, against the 12 months before. Fewer than 10 ready sales per bedroom count in those 12 months, so no yield is shown.

Bedrooms Median annual rent New contracts Change on a year earlier
4 BR AED 400,000 16 -3.6%

New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.

Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.

Mortgage registrations

Home mortgages DLD has registered on units in this project, per quarter, in the 12 quarters to 5 November 2026.

Mortgage registrations on homes per quarter. Source: DLD.

Mortgage registrations in the last 4 quarters (2026-Q1 to 2026-Q4): 6; registered amount AED 26.8M.

Since the first registration in 2015-Q4: 186 in all.

Counts DLD's mortgage registrations on homes in this project, including pre-registrations on off-plan units and lease-to-own registrations; portfolio and developer mortgages are left out. Amounts are the values DLD registers, shown for 5 registrations or more. A registration says nothing about the lender or the terms.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

The newest 10 of 2 registered sales in the 12 months to 5 November 2026
DateMarketType Size (sqft) Price (AED) AED/sqft
29 January 2026readyVilla 8,867 9,900,000 1,116
11 December 2025readyVilla 6,544 9,050,000 1,383
1 September 2025readyVilla 7,387 8,825,000 1,195
1 August 2025readyVilla 8,061 9,700,000 1,203
21 July 2025readyVilla 8,200 12,200,000 1,488
16 July 2025readyVilla 6,544 8,550,000 1,307
14 July 2025readyVilla 9,718 11,200,000 1,153
3 July 2025readyVilla 6,673 8,300,000 1,244
19 June 2025readyVilla 7,583 9,200,000 1,213
27 May 2025readyVilla 7,578 15,000,000 1,979

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

LocationWadi Al Safa 7 · Dubai Municipality community

Arabian Ranches II Park · 160 mPark · 410 mSchool · 640 mRanches Primary School · 670 mcarrefour market · 750 mGems Metropole School · 810 mPark · 810 mGrandiose Supermarket · 840 mSpinneys · 1 kmApproximate project location© OpenStreetMap contributors · Dubai Municipality · Makani
Approximate project location Malls and supermarkets Schools and hospitals Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

MallArabian Ranches Community Center · 2.4 km
Supermarketcarrefour market · 750 m
HospitalKings Hospital · 8.8 km
SchoolSchool · 640 m
ParkArabian Ranches II Park · 160 m

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors

New homes within 1.5 km

Open projects within 1.5 km of the pin: 2, with 484 units and villas.

2022: 112028: 473

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Wadi Al Safa 7: 6

Open projects in the same DLD area, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Reportage Village 1 25% Dec 2027 1,240 1,101
The Acres 2 & Estates 2 14.9% May 2028 — 208
The Acres 3 & Estates 14.9% Nov 2027 — 152
The Acres 25.2% — — 107
Mayfair Nexus by Seven Mayfair 0.6% Dec 2028 1,473 23
Palmarosa 97.8% Oct 2022 — 11

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Wadi Al Safa 7

Developer in DLD data Emaar Properties (P.J.S.C) · DLD developer no. 555

Projects registered
61
53 completed · 7 under construction · 1 not started
Units delivered
13,771
447 in the pipeline
Median build time
36 months
completed projects measured: 51
Past the DLD end date
0
of 4 under construction with a DLD end date

Completed a month or more after their DLD end date: 8 of 52 completed projects with both dates. In 41 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Emaar Properties (P.J.S.C) is one of 7 DLD-registered developers we list together as Emaar. See the group

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Questions about Arabian RANCHES- Rosa Community

When was Arabian RANCHES- Rosa Community completed?

Arabian RANCHES- Rosa Community is recorded as completed on 15 October 2016 (DLD register of 1 November 2026).

Who is the developer of Arabian RANCHES- Rosa Community?

Emaar Properties (P.J.S.C), as registered with DLD.

What is the DLD project number of Arabian RANCHES- Rosa Community?

1392.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error