DLD project no. 1753Completed32 units
Club Villas فيلات كلوب Completed 30 April 2019 (DLD) · DLD end date Apr 2019 · DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.
Completed projects cannot be added to My units.

CompletionDLD readings of % built, beside the share of the planned period gone
% built
28 October 2026| Date | % built | Source |
|---|---|---|
| 30 April 2019 | 100% | DLD inspection |
| 3 April 2019 | 96.3% | DLD inspection |
| 23 October 2018 | 90.4% | DLD inspection |
| 4 March 2018 | 87% | DLD inspection |
| 18 September 2017 | 80.1% | DLD inspection |
| 5 December 2016 | 40.1% | DLD inspection |
Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 5 August 2022, 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗
Site timeline
± 6 monthsOur imagery reading holds no milestone for this project yet.
Our reading of historical satellite imagery
Registered period and actual build
Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.
Changes in the DLD register
No change to the end date, status or % built across the register exports we hold.
Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.
DLD registration
DLD services ↗Homes: hotel apartments and rooms 10 · villas 22.
Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.
Description in the DLD register: Project is located in Palm Jumeirah community with 22 x B+G+1 Villas out of which 16 will be delivered as shell and core and Hotel Building which is also shell and core(BASEMENT+GR+FIRST+4 TYPICAL FLOOR+ROOF).
DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae
Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.
AED · sqft
No off-plan sales are registered for this project since 2020, so there is no launch price.
Prices are over villas and townhouses, the type most sales in this project are.
Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.
Median AED/sqft by quarter
2020-Q1 → 2026-Q2| Quarter | Registered sales | Median AED/sqft | DLD area Palm Jumeirah |
|---|---|---|---|
| 2020-Q1 | 1 (off-plan 0, ready 1) | — | 990 |
| 2020-Q2 | 1 (off-plan 0, ready 1) | — | 1,289 |
| 2020-Q3 | 2 (off-plan 0, ready 2) | — | 1,131 |
| 2021-Q2 | 5 (off-plan 0, ready 5) | 4,382 | 1,865 |
| 2021-Q3 | 6 (off-plan 0, ready 6) | 2,489 | 2,202 |
| 2021-Q4 | 2 (off-plan 0, ready 2) | — | 2,544 |
| 2022-Q2 | 1 (off-plan 0, ready 1) | — | 2,706 |
| 2022-Q4 | 1 (off-plan 0, ready 1) | — | 2,987 |
| 2023-Q1 | 2 (off-plan 0, ready 2) | — | 3,436 |
| 2025-Q3 | 1 (off-plan 0, ready 1) | — | 4,468 |
| 2026-Q2 | 1 (off-plan 0, ready 1) | — | 5,224 |
Median AED/sqft of registered sales per quarter (villas and townhouses). Source: DLD. Grey dashed line: DLD area Palm Jumeirah, median AED/sqft of ready sales of villas and townhouses by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.
Registered sales per quarter
| Quarter | Registered sales | Median AED/sqft | DLD area Palm Jumeirah |
|---|---|---|---|
| 2020-Q1 | 1 (off-plan 0, ready 1) | — | 990 |
| 2020-Q2 | 1 (off-plan 0, ready 1) | — | 1,289 |
| 2020-Q3 | 2 (off-plan 0, ready 2) | — | 1,131 |
| 2021-Q2 | 5 (off-plan 0, ready 5) | 4,382 | 1,865 |
| 2021-Q3 | 6 (off-plan 0, ready 6) | 2,489 | 2,202 |
| 2021-Q4 | 2 (off-plan 0, ready 2) | — | 2,544 |
| 2022-Q2 | 1 (off-plan 0, ready 1) | — | 2,706 |
| 2022-Q4 | 1 (off-plan 0, ready 1) | — | 2,987 |
| 2023-Q1 | 2 (off-plan 0, ready 2) | — | 3,436 |
| 2025-Q3 | 1 (off-plan 0, ready 1) | — | 4,468 |
| 2026-Q2 | 1 (off-plan 0, ready 1) | — | 5,224 |
Registered sales per quarter, off-plan and ready units. Source: DLD.
Service charges
What owners pay a year in completed buildings of the project’s master community, from their owners’ association budgets. A building’s own charge is set by its own budget.
Median AED per sq ft a year of residential owners’ association budgets, each development counted once, in the newest budget year with at least 10 developments. Plots, shared areas and hotel rooms are left out. A budget is not any one owner’s bill.
Source: Dubai Land Department, owners’ association budgets (service charges).
Registered sales
The newest sales DLD has registered in this project, as DLD publishes them.
| Date | Market | Type | Size (sqft) | Price (AED) | AED/sqft |
|---|---|---|---|---|---|
| 18 May 2026 | ready | Villa · 7 BR | 18,883 | 60,000,000 | 3,177 |
| 24 July 2025 | ready | Villa · 7 BR | 18,258 | 59,800,000 | 3,275 |
| 9 February 2023 | ready | Villa · 7 BR | 26,033 | 183,000,000 | 7,030 |
| 6 February 2023 | ready | Villa · 7 BR | 18,258 | 58,760,000 | 3,218 |
| 16 November 2022 | ready | Villa · 6 BR | 20,756 | 145,000,000 | 6,986 |
| 29 June 2022 | ready | Villa · 7 BR | 18,883 | 73,000,000 | 3,866 |
| 18 November 2021 | ready | Villa · 7 BR | 15,073 | 41,838,000 | 2,776 |
| 7 October 2021 | ready | Villa · 7 BR | 16,576 | 54,210,000 | 3,270 |
| 29 September 2021 | ready | Villa · 7 BR | 17,927 | 47,000,000 | 2,622 |
| 29 September 2021 | ready | Villa · 7 BR | 17,074 | 47,000,000 | 2,753 |
Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.
Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence
LocationNakhlat Jumeira · Dubai Municipality community
Places near the project
Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.
Dubai Municipality · Makani · © OpenStreetMap contributors · RTA
New homes within 1.5 km
Open projects within 1.5 km of the pin: 9, with 3,447 units and villas.
| DLD end year | Projects | Units and villas |
|---|---|---|
| 2026 | 1 | 448 |
| 2028 | 4 | 1,740 |
| 2029 | 2 | 398 |
| 2030 | 1 | 0 |
| 2031 | 1 | 861 |
Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.
Open projects in Nakhlat Jumeira: 21
Open projects in the same DLD area, by registered sales in 24 months.
| Project | Built | DLD end date | AED/sqft, 12 mo | Sales, 24 mo |
|---|---|---|---|---|
| Passo By Beyond | 0% | Dec 2029 | 6,160 | 281 |
| The Alba Residences by Omniyat | 8.4% | Mar 2028 | 9,123 | 55 |
| Palm Beach Towers - 2 | 81.6% | Dec 2026 | 3,287 | 53 |
| Palm Beach Towers -3 | 74.3% | Dec 2026 | 3,364 | 45 |
| Palm Beach Towers -1 | 82.8% | Dec 2026 | 3,295 | 43 |
| Olaia Residences | 14.3% | Dec 2027 | 4,028 | 36 |
| Como Residences | 24.8% | Mar 2027 | 5,624 | 25 |
| Vitalia by Pinnacle | 12.3% | Jun 2026 | — | 22 |
| Ocean House | 80.7% | — | 5,131 | 18 |
| Orla By Omniyat | 70% | Dec 2026 | 7,001 | 15 |
| ORLA Infinity by OMNIYAT | 61.3% | — | — | 7 |
| Ava At Palm Jumeirah By Omniyat | 95.9% | Jun 2026 | — | 6 |
AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.
Developer in DLD data Forum Group DMCC · DLD developer no. 983
Completed a month or more after their DLD end date: 0 of 1 completed projects with both dates. In 1 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.
Other projects in Palm Jumeirah
DLD lists 58 projects in the master project Palm Jumeirah.
Questions about Club Villas
When was Club Villas completed?
Club Villas is recorded as completed on 30 April 2019 (DLD register of 1 November 2026).
Who is the developer of Club Villas?
Forum Group DMCC, as registered with DLD.
What is the DLD project number of Club Villas?
1753.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error