DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Dubai off-plan projects 1,801 of 3,486 DLD projects are not yet completed: 1,239 under construction, 562 not started or pending. 227 under construction are past their DLD end date. DLD projects register, export of 1 November 2026 · sales to 5 November 2026

2,651–2,700 of 3,486 projects, most registered sales in 24 months first

2,651–2,700 of 3,486 projects, most registered sales in 24 months first
Project Developer DLD status Built DLD end date / completion Past DLD end date Sales, 24 mo
Signature Mansions2542 · Me'Aisem First · Jumeirah Golf EstatesSignature Jge Real Estate Development L.L.C Under construction 86.9% May 2026 5 mo past5 mo 5
Suncity Homes2067 · Warsan Fourth · International City Phase 3Sunn And Sand Developers Completed 100% Feb 2021 Completed— 5
Sunshine Residence1522 · Nadd Hessa · Silicon OasisSun And Sand Developers FZCO Completed 100% Dec 2016 Completed— 5
The Beachfront Villas By Ellington2894 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11Ellington Properties Development L.L.C Under construction 47.4% Aug 2026 2 mo past2 mo 5
The Galleries1765 · Nad Al Shiba First · Meydan Racecourse CommunityRockwell Real Estate Development L.L.C Completed 100% Feb 2019 Completed— 5
THE RESIDENCE | Burj Khalifa2443 · Burj Khalifa · DownTown DubaiEmaar Properties (P.J.S.C) Completed 100% Sep 2026 Completed— 5
The Tides By Amis4224 · Palm DeiraAmis Aurum Real Estate Development L.L.C Not started 0% Apr 2028 17 mo to go— 5
VELA by OMNIYAT2653 · Business BayDowntown Creek Real Estate Development L.L.C Under construction 50% — — 5
Victory Heights - Phase 21559 · Al Hebiah Fourth · Dubai Sports CityVictory Heights Real Estate Development L.L.C Completed 100% Dec 2015 Completed— 5
Zabeel Saray1041 · Palm JumeirahZabeel Investments (L.L.C) Completed 100% Nov 2009 Completed— 5
77S274 · Business Bay77 Shades Of Green Realestate Development L.L.C Under construction 13.7% Dec 2028 25 mo to go— 4
Bottega Nove by Lalav4324 · Wadi Al Safa 3 · MajanBottega Nove By Lalav Real Estate Development L.L.C Under construction 30% Jul 2027 8 mo to go— 4
Coventry 494392 · Madinat Al Mataar · Dubai South Residential DistrictGfs Wonders Developers L.L.C Not started 0% May 2028 18 mo to go— 4
Coventry Cove4466 · Saih Shuaib 2G F S Real Estate L.L.C Not started 0% Jul 2029 32 mo to go— 4
Damac Lagoons - Lagoon Views 12925 · Al Hebiah FifthIsland Oasis Properties Under construction 55.6% — — 4
Diamond Views 3 - Villas B1428 · Al Barsha South Fourth · Jumeirah Village CircleDiamond Developers CO.LIMITED Completed 100% Aug 2010 Completed— 4
Elaris Axis4212 · Al Barsha South Fifth · Jumeirah Village TriangleObject One Real Estate Development L.L.C Under construction 2.2% Nov 2028 24 mo to go— 4
Erantis344 · Al Barsha South Fourth · Jumeirah Village CircleCrown One Holding Limited Completed 100% Mar 2013 Completed— 4
Fairway Villas 32963 · Madinat Al Mataar · Dubai World CentralEmaar Dubai South DWC LLC Under construction 48.5% — — 4
Forum 23807 · Wadi Al Safa 3 · MajanK X G Real Estate Development L.L.C Under construction 7% Dec 2027 13 mo to go— 4
Golden Wood Views -12307 · Al Barsha South Fifth · Jumeirah Village TriangleGolden Wood Real Estate Development L.L.C Completed 100% Sep 2022 Completed— 4
Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 22001 · Al Merkadh · Mohammed Bin Rashid AL Maktoum City -District -1 CommunityDistrict One - FZ Completed 100% Jan 2022 Completed— 4
Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 292244 · Al Merkadh · Mohammed Bin Rashid AL Maktoum City -District -1 CommunityDistrict One - FZ Completed 100% May 2023 Completed— 4
Park Villa's 21536 · Al Barsha South Fourth · Jumeirah Village CircleArabian Gulf Properties Completed 100% Feb 2016 Completed— 4
Rabdan Square4401 · Nad Al Shiba First · Meydan Racecourse CommunityRabdan Square Developments L.L.C Under construction 1.2% Mar 2028 16 mo to go— 4
Royal Yacht Club Residence3770 · Palm DeiraAzimuth Development L.L.C Under construction 25.3% Nov 2027 12 mo to go— 4
Samana Miami2433 · Al Barsha South Fourth · Jumeirah Village CircleSamana Si Holding Limited Dubai Branch Completed 100% Jun 2026 Completed— 4
Serra Residence By Wujod4272 · Wadi Al Safa 2 · Liwan2Wujod Real Estate Development L.L.C Under construction 28.8% Dec 2027 13 mo to go— 4
The Derby Residence 2&31556 · Nad Al Shiba First · Meydan Racecourse CommunityR B A Real Estate Development L.L.C Completed 100% Apr 2015 Completed— 4
The Lakes Deema 31058 · Al Thanyah Third · Lakes - Deema 3Emaar Properties (P.J.S.C) Completed 100% Jan 2003 Completed— 4
The Rings2767 · Jumeirah Second · Dubai Water CanalP M R Development L.L.C Under construction 35.1% Dec 2025 10 mo past10 mo 4
Westar Casablanca989 · Al Barsha South Fourth · Jumeirah Village CircleWestar Properties Limited Completed 100% Jul 2015 Completed— 4
Westar Reflection167 · Al Barsha South Fourth · Jumeirah Village CircleWestar Properties Limited Completed 100% Feb 2011 Completed— 4
Ag Central2422 · Wadi Al Safa 5 · Dubai Land Residence ComplexAg Properties L.L.C Under construction 58.7% Oct 2026 under 1 mo past— 3
Al Vista3802 · BukadraDubai Investment Real Estate (L L C) Under construction 9.5% Oct 2027 11 mo to go— 3
Alicante villas2627 · Al Hebiah Fourth · Dubai Sports CityDubai Sports City (L. L. C) Completed 100% Sep 2025 Completed— 3
Arabian Ranches -La Avenida I1019 · Wadi Al Safa 6 · Arabian Ranches - 1Emaar Properties (P.J.S.C) Completed 100% Jan 2009 Completed— 3
Azizi Riviera 21955 · Al Merkadh · Meydan One CommunityAzizi Developments L.L.C Completed 100% Sep 2022 Completed— 3
Azizi riviera 583737 · Al Merkadh · Meydan One CommunityAzizi Developments L.L.C Completed 100% Aug 2026 Completed— 3
Cresswell Homes3299 · Madinat Al Mataar · Dubai South Residential DistrictAbdulwahed Faqeeh Properties L.L.C Under construction 28.9% Dec 2026 1 mo to go— 3
Damac Hills - BROOKFIELD-31356 · Al Hebiah Third · Damac HillsDamac Crescent Properties Completed 100% Dec 2014 Completed— 3
Damac Hills - The Trump Estates 32160 · Al Hebiah Third · Damac HillsDamac Crescent Properties Completed 100% Jun 2022 Completed— 3
Damac Hills -WHITEFIELD-21353 · Al Hebiah Third · Damac HillsDamac Crescent Properties Completed 100% Dec 2014 Completed— 3
Damac Islands - Maldives 23437 · Al Yelayiss 1Damac Elite Investment CO. L.L.C Under construction 14.1% Dec 2028 25 mo to go— 3
Damac Lagoons - Lagoon Views 32942 · Al Hebiah FifthIsland Oasis Properties Under construction 39.2% — — 3
Damac Lagoons - Lagoon Views 52944 · Al Hebiah FifthIsland Oasis Properties Under construction 42.3% — — 3
Diamond Views 4 - Villas A1431 · Al Barsha South Fourth · Jumeirah Village CircleDiamond Developers CO.LIMITED Completed 100% Jan 2012 Completed— 3
Dubai Hills - Hills Grove Community1399 · Hadaeq Sheikh Mohammed Bin Rashid · Dubai Hills EstateDubai Hills Estate L.L.C Completed 100% Feb 2018 Completed— 3
Dubai Water Front Veneto1167 · Hessyan First · VenetoDubai Waterfront (L.L.C) Completed 100% Feb 2015 Completed— 3
Elire3467 · Business BayQube Development L.L.C Under construction 8.2% Dec 2028 25 mo to go— 3

How to read this list

DLD status
Under construction, not started, pending or completed, as the Dubai Land Department records it. The status filter counts not started and pending together.
Built
The latest % complete that DLD publishes for the project.
DLD end date
The completion date in the DLD register, with whole months to go from the export date.
Past DLD end date
Whole months since the DLD end date, for projects DLD still lists as under construction.
Sales, 24 mo
Sales of units in the project registered with DLD in the last 24 months.