DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Dubai off-plan projects 1,801 of 3,486 DLD projects are not yet completed: 1,239 under construction, 562 not started or pending. 227 under construction are past their DLD end date. DLD projects register, export of 1 November 2026 · sales to 5 November 2026

1,201–1,250 of 3,486 projects, most registered sales in 24 months first

1,201–1,250 of 3,486 projects, most registered sales in 24 months first
Project Developer DLD status Built DLD end date / completion Past DLD end date Sales, 24 mo
Damac Casa2801 · Al Safouh Second · Site AAqua Viridis Investment L.L.C Under construction 33.6% — — 68
Forest City Tower 23727 · Wadi Al Safa 5 · Dubai Land Residence ComplexAl Helal Al Zahaby Real Estate Development L.L.C Under construction 1.2% Jun 2027 7 mo to go— 68
Golden Woods Albab Views3591 · Madinat Al Mataar · Dubai South Residential DistrictA G W Real Estate Development L.L.C Under construction 30.1% Feb 2027 3 mo to go— 68
Grand Views1601 · Nad Al Shiba First · Meydan Racecourse CommunityG&CO Real Estate Development LLC - FZ Completed 100% Nov 2019 Completed— 68
Greenview2157 · Madinat Al Mataar · Dubai World CentralEmaar Dubai South DWC LLC Completed 100% Jan 2024 Completed— 68
Haven Bay Residences3101 · Palm DeiraMetac Properties L.L.C Under construction 82.9% Jun 2026 4 mo past4 mo 68
J1884145 · Al Jadaf · Sama Al JadafJad Global Real Estate Development L.L.C Not started 0% Apr 2028 17 mo to go— 68
Ontario Tower349 · Business BayRose Homes Investment (L.L.C) Completed 100% Aug 2010 Completed— 68
Signature Livings1929 · Al Barsha South Fourth · Jumeirah Village CircleGreen Properties Development CO. L.L.C Completed 100% Mar 2021 Completed— 68
The Diplomat Residences2524 · Al Yelayiss 2 · Town SquareNshama Properties Owned By Nshmi Development One Person Company L.L.C Completed 100% Nov 2024 Completed— 68
The Haven Garden2772 · Al Barsha South Fourth · Jumeirah Village CircleMetrical Real Estate Development L.L.C Completed 100% Apr 2026 Completed— 68
Tiara Residence1040 · Palm JumeirahZabeel Investments (L.L.C) Completed 100% Oct 2009 Completed— 68
Time 11973 · Wadi Al Safa 5 · Dubai Land Residence ComplexTime Properties Completed 100% Dec 2022 Completed— 68
Warsan Village A1384 · Al Warsan First · International City Phase 1International City ( L.L.C ) Completed 100% Mar 2016 Completed— 68
Aura Prestige3788 · Nadd Hessa · Silicon OasisAura Infinite Real Estate Development L.L.C Under construction 40.1% Nov 2026 under 1 mo past— 67
Chic Tower2460 · Business BayPax Investment L.L.C Under construction 84% Jul 2025 15 mo past15 mo 67
Elevia Residences3635 · Warsan Fourth · International City Phase 3Valores Property Development L.L.C Under construction 9.2% Jun 2027 7 mo to go— 67
Enqlave By Aqasa2959 · Jabal Ali First · Discovery GardensAqasa Homes Developers L.L.C Under construction 70.3% — — 67
Glitz Residence 31655 · Al Hebiah Second · Dubai Studio CityDanube Properties Development L.L.C Completed 100% Nov 2017 Completed— 67
Mercedes-Benz Places | Binghatti2545 · Burj Khalifa · DownTown DubaiBinghatti Developers FZE Under construction 65.3% Dec 2026 1 mo to go— 67
Seaside by Prestige One3119 · Palm DeiraPrestige The Seaside Real Estate Development L.L.C Under construction 43% Dec 2026 1 mo to go— 67
Solanki One3776 · Wadi Al Safa 5 · Dubai Land Residence ComplexSolanki Real Estate Development L.L.C Under construction 35.2% May 2028 18 mo to go— 67
Solaya (1,2,3)4089 · Jumeirah First · La MerLa Mer North Property CO. L.L.C Not started 0% Jun 2029 31 mo to go— 67
Urbana Iii1880 · Madinat Al Mataar · Dubai World CentralEmaar Dubai South DWC LLC Completed 100% May 2020 Completed— 67
Arabella 31877 · Al Hebiah Sixth · MudonMdn Real Estate L.L.C Completed 100% Jul 2020 Completed— 66
Arbor View2814 · Al Barshaa South Third · ArjanE L P D Developers L.L.C Completed 100% Apr 2026 Completed— 66
Art House Hills by Adaan and Tuscany4235 · Al Barshaa South Third · ArjanArt House Hills Residences Development L.L.C Not started 0.2% Dec 2028 25 mo to go— 66
Azha Millennium Residences3482 · Al Barsha South Fifth · Jumeirah Village TriangleAzha J V T Residences L.L.C Under construction 30.1% Sep 2027 10 mo to go— 66
Azizi Venice 12821 · Madinat Al Mataar · Dubai World CentralAzizi Developments L.L.C Under construction 67.4% Dec 2025 10 mo past10 mo 66
Binghatti Apartments1630 · Nadd Hessa · Silicon OasisBinghatti Developers FZE Completed 100% Dec 2015 Completed— 66
Binghatti Creek2361 · Al Jadaf · Dubai Health Care City Phase 2Binghatti Developers FZE Completed 100% Apr 2023 Completed— 66
Cherrywoods2171 · Al Yelayiss 1Al Qudra Estates L.L.C Completed 100% Jun 2021 Completed— 66
Club Drive2769 · Hadaeq Sheikh Mohammed Bin Rashid · Dubai Hills EstateDubai Hills Estate L.L.C Completed 100% Oct 2026 Completed— 66
Damac Hills (2) - AVENCIA-21866 · Madinat Hind 4 · Damac Hills 2Front Line Investment Management L.L.C Completed 100% Aug 2022 Completed— 66
Damac Hills (2) - Navitas (A & B)2184 · Madinat Hind 4 · Damac Hills 2Front Line Investment Management L.L.C Completed 100% Jun 2023 Completed— 66
Fior 14287 · Madinat Dubai Almelaheyah · Mina RashidMina Rashid Properties L.L.C Not started 0% Jul 2030 44 mo to go— 66
Grove2850 · Al Yelayiss 2 · Town SquareNshama Properties Owned By Nshmi Development One Person Company L.L.C Under construction 40.7% — — 66
Lilian Residences3468 · Madinat Al Mataar · Dubai South Residential DistrictLondon Gate Real Estate Development L.L.C Under construction 4.7% Apr 2028 17 mo to go— 66
MAG2181145 · Marsa Dubai · Dubai MarinaDream Estate Limited Completed 100% May 2010 Completed— 66
Mass Residence3182 · Al Barsha South Fourth · Jumeirah Village CircleJaiedco Real Estate Development L.L.C Completed 100% Jan 2025 Completed— 66
New Dubai GATE1407 · Al Thanyah Fifth · DMCC Master CommunityBonyan International Investment Group (Holding) (L.L.C) Completed 100% Mar 2010 Completed— 66
Oasis Residences3726 · Madinat Al Mataar · Dubai South Residential DistrictAl Helal Al Zahaby Real Estate Development L.L.C Under construction 35.3% Jul 2027 8 mo to go— 66
Sunset Bay One By Imtiaz3460 · Palm DeiraImtiaz Sunset Real Estate Development L.L.C Under construction 78% Dec 2026 1 mo to go— 66
Sunset Bay Two By Imtiaz3570 · Palm DeiraImtiaz Real Estate Investment & Development L.L.C Under construction 70.2% Feb 2027 3 mo to go— 66
The Orchard Place2629 · Al Barsha South Fourth · Jumeirah Village CirclePeak Summit Real Estate Development L.L.C Under construction 42.7% Jul 2026 3 mo past3 mo 66
Vyb2727 · Business BayGinco Properties L.L.C Completed 100% Jun 2026 Completed— 66
Azizi Riviera 462294 · Al Merkadh · Meydan One CommunityAzizi Developments L.L.C Completed 100% Jan 2024 Completed— 65
Bali Residences2472 · Al Barsha South Fifth · Jumeirah Village TriangleBali Builders Real Estate Development Completed 100% Dec 2023 Completed— 65
Gateway By Premier Choice2688 · Al Barsha South Fourth · Jumeirah Village CircleP C I Real Estate Developers L.L.C Under construction 68% — — 65
Petalz By Danube2495 · Al Warsan First · Warsan First DevelopmentDanube Properties Development L.L.C Completed 100% Oct 2025 Completed— 65

How to read this list

DLD status
Under construction, not started, pending or completed, as the Dubai Land Department records it. The status filter counts not started and pending together.
Built
The latest % complete that DLD publishes for the project.
DLD end date
The completion date in the DLD register, with whole months to go from the export date.
Past DLD end date
Whole months since the DLD end date, for projects DLD still lists as under construction.
Sales, 24 mo
Sales of units in the project registered with DLD in the last 24 months.